Re: Baseline not shown after wizard formatting



Have you first saved a baseline via Tools, Tracking, Save Baseline?

--

Rod Gill
Project MVP
Visit www.msproject-systems.com for Project Companion Tools and more


"Mary_tgd" <Mary_tgd@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:404E6E3F-D8F9-4ABA-ACF6-C66F12993659@xxxxxxxxxxxxxxxx
I've tried to set baseline using wizard formatting but baseline bar does
not
shown on the gantt chart. The software I'm using is Microsoft Project
Standard 2003.


.



Relevant Pages

  • Re: Why does changing remaining work also change the Work column?
    ... Visit www.msproject-systems.com for Project Companion Tools and more ... "Rod Gill" wrote: ... Tools, Tracking, save baseline. ... View the Tracking Gantt chart to see where you are ...
    (microsoft.public.project)
  • Re: How to stop Baseline date changing to match Actual date entry?
    ... Rod Gill wrote: ... Baseline Finish but in reality it's a different column altogether and not ... Visit www.msproject-systems.com for Project Companion Tools and more ... Those fields change when you enter Actuals. ...
    (microsoft.public.project)
  • Re: How to print a few tasks of a project
    ... Tables decide which columns show and filters determine which "rows" show. ... "Rod Gill" wrote: ... Visit www.msproject-systems.com for Project Companion Tools and more ... my Gantt Chart View. ...
    (microsoft.public.project)
  • Re: MS Project - Manage several hundred projects that have the sam
    ... what about using Project in its Enterprise mode? ... "Rod Gill" wrote: ... > Visit www.msproject-systems.com for Project Companion Tools and more ... >> The scope of work is the same for each location/store. ...
    (microsoft.public.project)
  • Re: Filter Removes Blank Tasks
    ... The bottom line is that blank tasks are an extremely bad idea in Project's task tables and if you include them, sooner or later it's going to rear up and bite you on the backside. ... "Rod Gill" wrote: ... summary tasks in your filter, ... >> Visit www.msproject-systems.com for Project Companion Tools and more ...
    (microsoft.public.project)