Re: Task Delegation Problem
- From: "Dale Howard [MVP]" <dale(dot)howard(at)msprojectexperts(dot)com>
- Date: Thu, 27 Jul 2006 08:14:58 -0600
Ravikumar --
You are more than welcome, my friend! :)
--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We wrote the book on Project Server"
"Ravikumar G" <RavikumarG@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:D92BA1DE-697B-4E54-A38E-C8F8E59AD7B5@xxxxxxxxxxxxxxxx
Thanks and sorry for posting in the wrong area. I have done this but not
worked for me. Later I changed the permission settings of my resources to
allow the users to view assignment, and now its working. thanks for your
quick help.
"Dale Howard [MVP]" wrote:
Ravikumar G --
In the future, please post your question in the
microsoft.public.project.server newsgroup, as this newsgroup is devoted
to
the Microsoft Project desktop application only. To answer your question,
do
the following:
1. Log into PWA with administrator permissions
2. Click Admin - Manage Security
3. Select the My Tasks category and click the Modify Category button
4. In the Resources section, select the "All current and future
resources..." option
5. Click the Save Changes button
Hope this helps.
--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We wrote the book on Project Server"
"Ravikumar G" <Ravikumar G@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:B644AFAA-0616-4046-B0CF-A31F75B62508@xxxxxxxxxxxxxxxx
Hi All,
Am using the MSP 2003 and Proj Prof 2003 combo. I have added few
resources
from active directory and have one project created from a PM account.
Now
the
assigned resource when trying to delegate the task, first it did not
show
delegate option. Then we enable delegation in global permissions and
respective in category permissions. After getting the Delegate option
enabled, when clicking on the task, it says
"There are no resources available to delegate tasks.
You either do not have permissions to see the assignments of any
resources
or there are currently no resources in the Project Server database
other
than
your account. Contact your server administrator. "
pl help me in this.. what could be a problem in making a team member
eligible to delegate a task.
.
- References:
- Re: Task Delegation Problem
- From: Dale Howard [MVP]
- Re: Task Delegation Problem
- Prev by Date: Re: How shall I prioritize the risks of a project??
- Next by Date: Re: Showing holiday per resource in a report
- Previous by thread: Re: Task Delegation Problem
- Next by thread: Re: Exporting/extracting data from resource calendars
- Index(es):
Relevant Pages
|