Re: Resource work



Hi Andrew,

Welcome to this Microsoft Project newsgroup :)

No, I don't know why :( However, with more information we might be able to
help. Try creating a new file with a few tasks and resources. Do what you
did before and see if you get the same results. As Duration = Work X Units,
you cannot have a change to one without one of the other parameters
changing. Unless, somehow, there is some corruption. I hope you have kept
backups of the originals. Try renaming one of them and see if you still
have problems. Give us an example of what the task parameters were before
and after. That'll do for the moment!

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials

Andrew wrote:
To further all of my problems it has only change the work and kept
the units % the same the task is on fixed duration and not effort
driven, need help really badly

Andrew

"Andrew" wrote:

Hey people just have a quick question i have 62 project alll
seperat files, i baselined them all and then when i saved them and
closed it and 1 hour later it got re openned it had dropped exactly
50% of the work from the resource. does any one know why??

thanks

Andrew



.



Relevant Pages

  • Re: % Work Complete Variance
    ... Andrew and Jim thanks very much to both of you for your. ... all resources and assigning those resources to all tasks. ... What do i do for projects that already have a baseline created and Actual ... standard rate to resources), i will be set up to solve the problem i was ...
    (microsoft.public.project)
  • Re: How can I get my resources back?
    ... fix the problem. ... Andrew J. Rozsa wrote: ... the fewer resources ...
    (microsoft.public.win2000.general)
  • Re: F-Prot for BSD WorkStation
    ... Andrew L. Gould wrote: ... >> You might find that doing the full system scan takes up a lot of resources ... > If resource utilization is an issue, the scanning strategy could be changed to ...
    (freebsd-questions)
  • Re: Standard Resource Listing - not Resource Pool
    ... You're welcome Andrew. ... feedback. ... resources in it and I just copy all the resources and paste into ... on another project to avoid the copy/paste step. ...
    (microsoft.public.project)