Re: how do i separate split duration of total duration in msp ?

Tech-Archive recommends: Fix windows errors by optimizing your registry



Are you using the "Split Tasks" tool on the toolbar to put a break (indicated by dots) in the middle of the task? If so you don't need to worry about it, the duration Project shows only includes the parts on either side of the break. Try it. Create a new file with a single task X with 2 weeks duration. Click the Split Tasks tool, click in the middle of your task bar, and drag it out to the right a week or so. Now you'll see the start and finish are 3 weeks apart but the duration field still shows 2 weeks. Remember that duration does not include non-working time and when you split the task the time during the split gets marked as non-working as far as that specifc task is concerned.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs

"heidaripm" <heidaripm@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message news:EC4C1919-3914-4AE9-8DFC-89BA97A6C877@xxxxxxxxxxxxxxxx
i have some tasks was splited in my plan .i want to calculate actual
progress so i need to separate the split duration of total duration so i want
the split duration hasn't in my caculation . how can do that ?

.



Relevant Pages

  • Re: Bars different sizes in gantt chart view
    ... Kind regards, ... In the Gantt Chart view, right click in a blank area of the chart, select ... I see what Project is doing now wrt the non-working time over ... I've set the calendar working time to 10 hours/day and the duration for a ...
    (microsoft.public.project)
  • Re: Bars different sizes in gantt chart view
    ... In the Gantt Chart view, right click in a blank area of the chart, select Layout... ... and uncheck "Round bars to whole days". ... I see what Project is doing now wrt the non-working time over ... I've set the calendar working time to 10 hours/day and the duration for a ...
    (microsoft.public.project)
  • Re: Bars different sizes in gantt chart view
    ... I see what Project is doing now wrt the non-working time over ... I've set the calendar working time to 10 hours/day and the duration for a ... and range from 2.5 hrs to 5 hrs and so on. ... Duration is a measure of working time, so a 5 day task shows a longer bar ...
    (microsoft.public.project)
  • Re: Bars different sizes in gantt chart view
    ... Kind regards, ... In the Gantt Chart view, right click in a blank area of the chart, select ... > I've set the calendar working time to 10 hours/day and the duration for> a ... >>> non-working time, but the task durations I'm trying to indicate, are ...
    (microsoft.public.project)
  • Re: Sub Task Length
    ... In addition to my companion's comments, I might mention that a 4-month duration task starting 01 Sept WILL NOT end 31 Dec. ... the normal days, weeks, or months of the normal calendar we use every day but rather it is the working-time minute. ... Days off, holidays, non-working time when the resources go home to eat and sleep, etc, are all deducted from the 24 hour civil day. ... Task1 lasts 20 days ...
    (microsoft.public.project)