Re: Help- How do I change default hours per day



4 hours sounds like the team is just working half their day on your project?
If so, the simplest solution is to go to the Resource Sheet and set the
teams' Max Units to 50%. Then only assign them at 50% which will only ever
see them doing a maximum of 4 hours work a day.

--

Rod Gill
Project MVP
Visit www.msproject-systems.com for Project Companion Tools and more


"hll" <hll@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:F15EDB7C-76F1-44A8-B983-F405C96630ED@xxxxxxxxxxxxxxxx
I want to change the default hours a team works in MS Project 2003
Professional. For example, the default time is 8:00am to 12:00pm and then
1:00pm to 5:00pm. I need to change this to reflect a 4 hour work days of
7:00am to 11:00am. I know I can change it by selecting every day and
making
them "non-default working times" but I need to make a claendar or template
that can be used by all with this as a standard. There has got to be a
way...

Help



.