Re: Baseline vs actual schedule and start/finish dates



Why should the baseline and actuals match??? The baseline reflects what you thought was going to be the duration. The actual is what it really did turn out to require. OF course they may be different, in fact, it's very likely that they WILL be different in a lot of cases. The baseline is a record of your initial estimate and estimates always have a certain level of uncertainlty in them.

"lili" <lili@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message news:17CB781E-F0ED-400A-9218-457B8C1C1881@xxxxxxxxxxxxxxxx
I have establishd a basesline schedule and have been maintaining the schedule
using actual start and actual finish columns. I have many linked tasks.
Project automatically updates (i.e. projects the actual start/finish date)
as I update the actual start and finish columns because the activities are
linked. However, the durations of these projected durations don't match the
baseline durations. Essentially, the projected actual start and finish dates
don't represent how the schedule has changed as a result of the real actual
start and finish dates.

My project runs 7 days/week, 12 hours/day. At first I thought the durations
were "skipping" weekends but I selected all tasks and resources and assigned
them all to the custom calendar with no change to the projected actual
durations.

How can I make the "actual" projected durations match the baseline durations?


.



Relevant Pages

  • Re: new project dates to auto fill
    ... > like to be able to enter a start date (baseline) and according to the ... estimated Durations and inter-dependencies between tasks. ... Once your plan is as you want it (i.e. all necessary tasks are included ... to achieve the end goal, usually some completion milestone, and the ...
    (microsoft.public.project)
  • Re: updating a project tasks and durations
    ... You save the baseline after the plan is finalized as a reference against which you track progress. ... So if you start with a generic template any baseline associated with it is meaningless and should be discarded as that doesn't represent the "real" project plan you will be working. ... You customize the plan, dropping tasks that are unnecessary due to differences in scope between this plan and the template it's based on, adding other tasks if required, estimate durations for individual tasks Then after the plan is approved and before any work is performed, you create the baseline so you'll later be able to measure actual performance against the plan you envisioned so you can tell if you're on-time or not and are staying within your budget. ...
    (microsoft.public.project)
  • Re: statistical graph showing percentages
    ... predicted task durations (baseline). ... "predicted task durations" and how that relates to task completions. ... The first filter would find all tasks that are between month ...
    (microsoft.public.project)
  • Re: Baseline vs actual schedule and start/finish dates
    ... There is no point having a baseline if it "must" match the Actuals. ... Project automatically updates ... the durations of these projected durations don't match ...
    (microsoft.public.project)
  • Re: Baseline vs actual schedule and start/finish dates
    ... I have many linked tasks. ... Project automatically updates ... the durations of these projected durations don't match the ... How can I make the "actual" projected durations match the baseline durations? ...
    (microsoft.public.project)