Re: Baseline vs actual schedule and start/finish dates

Tech Tip: Click here to run a free scan for Windows Errors and optimize PC performance



Hi Lili,

The purpose of a baseline is to serve as a comparison basis to see by how
much the actual situation deviates from the original one.
There is no point having a baseline if it "must" match the Actuals.
Actuals are dictated by reality, so they should not (always) be a copy of
the original plan!
HTH

--
Jan De Messemaeker, Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
For FAQs: http://www.mvps.org/project/faqs.htm
"lili" <lili@xxxxxxxxxxxxxxxxxxxxxxxxx> schreef in bericht
news:17CB781E-F0ED-400A-9218-457B8C1C1881@xxxxxxxxxxxxxxxx
I have establishd a basesline schedule and have been maintaining the
schedule
using actual start and actual finish columns. I have many linked tasks.
Project automatically updates (i.e. projects the actual start/finish date)
as I update the actual start and finish columns because the activities are
linked. However, the durations of these projected durations don't match
the
baseline durations. Essentially, the projected actual start and finish
dates
don't represent how the schedule has changed as a result of the real
actual
start and finish dates.

My project runs 7 days/week, 12 hours/day. At first I thought the
durations
were "skipping" weekends but I selected all tasks and resources and
assigned
them all to the custom calendar with no change to the projected actual
durations.

How can I make the "actual" projected durations match the baseline
durations?



.



Relevant Pages

  • Re: new project dates to auto fill
    ... > like to be able to enter a start date (baseline) and according to the ... estimated Durations and inter-dependencies between tasks. ... Once your plan is as you want it (i.e. all necessary tasks are included ... to achieve the end goal, usually some completion milestone, and the ...
    (microsoft.public.project)
  • Re: updating a project tasks and durations
    ... You save the baseline after the plan is finalized as a reference against which you track progress. ... So if you start with a generic template any baseline associated with it is meaningless and should be discarded as that doesn't represent the "real" project plan you will be working. ... You customize the plan, dropping tasks that are unnecessary due to differences in scope between this plan and the template it's based on, adding other tasks if required, estimate durations for individual tasks Then after the plan is approved and before any work is performed, you create the baseline so you'll later be able to measure actual performance against the plan you envisioned so you can tell if you're on-time or not and are staying within your budget. ...
    (microsoft.public.project)
  • Re: statistical graph showing percentages
    ... predicted task durations (baseline). ... "predicted task durations" and how that relates to task completions. ... The first filter would find all tasks that are between month ...
    (microsoft.public.project)
  • Re: Baseline vs actual schedule and start/finish dates
    ... The baseline reflects what you thought was going to be the duration. ... I have many linked tasks. ... Project automatically updates ... the durations of these projected durations don't match the ...
    (microsoft.public.project)
  • Re: How to split tasks and show correct duration without elapsed t
    ... MS Project MVP ... See http://tinyurl.com/2xbhc for my free Project Tutorials ... start date to the date I wanted, reenter actuals. ... Please note that no elapsed durations ...
    (microsoft.public.project)