Re: How can I add funding totals per year in Project across an activit



Hi,

Everything is possible, except totals at the bottom: Project makes totals at
the top.
In Task Usage, create a timescale with the minor scale years (this also the
middle scle years)

Then Tools, Options, view, click on Project Summary task.
HTH

--
Jan De Messemaeker, Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
For FAQs: http://www.mvps.org/project/faqs.htm
"Carlos" <Carlos@xxxxxxxxxxxxxxxxxxxxxxxxx> schreef in bericht
news:DDF358ED-ED03-4730-9C10-ECEBB391924D@xxxxxxxxxxxxxxxx
I would like to maintain/show cost per year per activity and totals per
year
at the bottom.


.



Relevant Pages

  • Re: Actual Work for Individual resources at summary task level
    ... into Project in the Task Usage view. ... are assigned at the task level and we need totals by week ... >resource's assignment total for that summary level. ... >few resources, individual spare fields could be used so ...
    (microsoft.public.project2000)
  • Re: TOTAL COST COLUMN (IN TASK USAGE VIEW)
    ... You mention the Task Usage view but you don't talk about whether you ... simple macro to transfer the custom field values from a Resource view ... If you are interested in timescale values then you have no choice but to ... Project MVP ...
    (microsoft.public.project)
  • Re: Copying Usage Views to Excel
    ... I was able to copy multiple columns of data from the ... tier of the timescale. ... How do I copy a Task Usage or Resource Usage view to Excel. ... successfully Ctl/C and paste the timescaled data as separate columns? ...
    (microsoft.public.project)
  • Re: Cost per fiscal year
    ... Take a look at the Task Usage view. ... I would add Cost and Cumulative Cost ... year and the timescale in either usage view is set for fiscal year, ... Microsoft Project ...
    (microsoft.public.project)
  • Re: Splitting a task by less than a day
    ... > Show Task usage with a timescale by the hour, ... >> member to stop half way through for a half day meeting. ... >> Resource Usage views but all it makes the staff member ...
    (microsoft.public.project)