What is the best way to add buffer work in a project plan

Tech-Archive recommends: Repair Windows Errors & Optimize Windows Performance



Hi All,

What is the best or the most optimized way to add buffer resources in
an MPP?

Scenario -
Planning for a phase in the SDLC of a software project. Plan might look
like:
1. Phase 1 - 1 Jan - 31 Jan - 22 days - 176 hrs
1.1 Analysis - 1 Jan - 10 Jan - 7 days - 56 hrs
1.2 Design - 11 Jan - 13 Jan - 3 days - 24 hrs
1.3 Coding - 16 Jan - 20 Jan - 5 days - 40 hrs
1.4 Testing - 23 Jan - 31 Jan - 7 days - 56 hrs

In this scenario, i would like to make some provision for buffer
effort. I would like to add a Task 1.5 - Rework for 10 hour of work in
between 16 Jan - 31 Jan ( duration of 12 days )

What could be the best way to add this effort?

Postscripts:
1. The tasks are fixed unit tasks
2. One possible solution would be add a task as the next line item and
manually set the work to 10 hours and duration to 12 days with starting
day as 16 Jan,; and then allocate a resource.

Is there any other option or mehtodology?

Much Rgds
Jay

.



Relevant Pages

  • Re: too much ARP traffic! help!
    ... Ouch, that is the worst possible scenario. ... when planning everything, so that there were always someone who could ... (replace 'badnews' with 'news' in e-mail address) ...
    (comp.security.firewalls)
  • Re: Replicating AD to another server
    ... I was planning on running DFS anyway. ... Think this scenario ... Jude ...
    (microsoft.public.windows.server.active_directory)