Re: Updating via timesheet

Tech-Archive recommends: Fix windows errors by optimizing your registry



Mike --

Totally awesome! Thanks for your wisdom... :)

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We wrote the book on Project Server"


"Mike Glen" <glenATmvps.org> wrote in message
news:uzWiFlseGHA.3572@xxxxxxxxxxxxxxxxxxxxxxx
Well...

As I said in http://project.mvps.org/networkanalysis.htm , I believe in
taking tasks down to using the doing words: painting, cutting,
programming, printing, writing, etc. Getting down to the nitty gritty is
absolutely essential. How far do you go? Well, you have to take the
expertise of the resource into account. If you want an electrical socket
placed on a wall, I would assume a qualified electrician would do the job.
In which case the task would be to fit socket at point x. If you get to
the stage of writing tasks that start "pick up screwdriver...", then
you've gone too far! Equally, a task that says "Fit sockets to walls" is
far too vague or high level. Getting the balance right is important, and
requires the application of skill and experience. No project planners can
have all the experience to know it all, so one has to ask the expert to
break the task down to its elements. If anything, it is better to plan to
too much detail than too little, as you can always amalgamate or delete
tasks, but it is much more difficult to add tasks and will almost
certainly result in delays and missed deadlines.

However these are rules of thumb. If you're setting up an experiment in a
lab that last a few minutes, getting the sequence right is just as
important as it is in enumerating the tasks nessary to build an aircraft.
The scale is differet - the principles are the same. Hence one cannot be
too dogmatic on length of tasks or how many - you need just enough, which
only life and experience can tell you. However, for beginners, I would
use as a rule of thumb for a 3 month project, to have tasks no longer than
10 days and no shorter than 1 day. I would call for weekly reports to
begin with and ask for more or less frequent reports as experience then
dicatates. I would expect local management to make up for lost time,
delays , etc, by working overtime, bringing in extra resources or
whatever, reporting to you only when in trouble from which they can't see
a solution. I would see a reschedule and a new plan to be issued after
the first month and again after the second, then run out the plan making
last minute ad hoc changes to get the job finished, all the while with
crossed fingers!

I'm an avocate of one resource per task if at all possible. Detailed
planning is essential. However, be aware of the level of management
needed. Over-management of the detail can be just as destructive as
under-management. Always consider what level of interfenence you need to
apply to manage the situation - can local management cope or do you need
to interject?

Enough of my ramblings this time of night - I must retire to bed now.:)


Mike Glen
Project MVP







.


Quantcast