Re: Delaying a task

Tech-Archive recommends: Speed Up your PC by fixing your registry



Hasn't this been discussed many times?
Or have I missed something?
Was it fixed while I wasn't looking?

Hasn't it been noted that ALAP in MSP will soak up all of the float in all
of the Task's non-critical successors.

All that's needed is a constraint which sets the ES equal to the LS so that
the Task that we're interested in gives up all of its free slack (float).

MSP doesn't have it. MSP's ALAP is too strong and there is no alternative
(except P* which does have a zero free float and zero total float
constraint).

"John" <mjensen@xxxxxxxxxxxx> wrote in message
news:mjensen-6264F7.13093212052006@xxxxxxxxxxxxxxxxxxxxxxx
In article <70B32771-A782-493E-9B1E-B6F29DF02DE2@xxxxxxxxxxxxx>,
txtoto <txtoto@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote:

How do I delay a task to the maximum amount without shifting the task
it's
linked to?

txtoto,
By not impacting the task it's linked to I assume you mean not slipping
the successor. Set a constraint of "As late as possible".

John
Project MVP


.



Relevant Pages

  • Re: Delaying a task
    ... Hasn't it been noted that ALAP in MSP will soak up all of the float in all ... All that's needed is a constraint which sets the ES equal to the LS so that ... MSP doesn't have it. ...
    (microsoft.public.project)
  • Re: Total slack not correct
    ... One wrinkle here is Project doesn't do quite what I would expect regardling the placement of tasks viz a vie ASAP and ALAP when scheduling backwards. ... Now in the advance tab of the task information change the constraint to ASAP. ... If however I add another task that is 10 days duration that new task begins 05 Dec and now the first task moves so that it also starts 05 Dec and picks up 5 days slack. ...
    (microsoft.public.project)
  • Re: How to enter dates in MS Project
    ... predecessors to Tasks in my project, and have no predecessors in my project ... practice in the construction industry, with MSP but especially with P3, ... constraint date within the project plan as handled by MS Project. ...
    (microsoft.public.project)
  • Importing duration and constraint date
    ... I have an Excel sheet with Constraint date, ... The Constraint Type is added automatically. ... I tell MSP: import this. ... Add a column for Constraint Type and type "start no earlier than" ...
    (microsoft.public.project)
  • Re: schedule backward and forward?
    ... ALAP indeed makes the task and its complete successor chain critical. ... constraint, so when I apply the ALAP to them, it shoots them out after the ... BOTH forward and backward. ... I am setting up a schedule for a future project, ...
    (microsoft.public.project)