Re: How to assign the same resource to the same task?
- From: "Steve House [Project MVP]" <sjhouse.remove@xxxxxxxxxxxxxxxxxx>
- Date: Wed, 10 May 2006 07:21:53 -0400
Though I don't know your exact situation, most likely these are NOT the same task in fact but rather multiple occurances of similar tasks. A task is a discrete block of work that results in a single deliverable. If your resource is re-visiting these tasks over a number of years it's very likely that each "visit" results in its own unique deliverable and thus is really each reptition is separate independent task with similar work activity to the others. If I have to paint the walls of my room, each wall takes 1 day, and I'm going to do one wall a month, it's not one task lasting 4 months, it's 4 different 1-day tasks each involving painting a wall.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs
"Ollie" <Ollie@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message news:08AA7761-350B-4996-8CE5-CAFBEE38DAAD@xxxxxxxxxxxxxxxx
Dear Project Team,
I'm running into an assignment problem.
How do I assign the same resource multiple times to the same task?
In other words, I have the same person work at different times on the same
task.
FYI: I'm want to track up to 700 tasks with about 20 resources and the
resources visiting and re-visiting the same tasks multiple times over years
to come.
Thank you for your help.
Best wishes,
Oliver Zieseniss
.
- Prev by Date: Re: % complete of a task moving back to before today's date
- Next by Date: Re: % complete of a task moving back to before today's date
- Previous by thread: Re: How to assign the same resource to the same task?
- Next by thread: Re: Leveling of Recurring tasks
- Index(es):
Relevant Pages
|