Re: split task without chaging end date
- From: "Rod Gill" <rod AT project-systems DOT co DOT nz>
- Date: Thu, 20 Apr 2006 22:56:21 +1200
Yes. View the Task Usage and for the days you want the Task to show no bar,
enter 0d in the Work row.
--
Rod Gill
Project MVP
Visit www.msproject-systems.com for Project Companion Tools and more
"ellebelle" <ellebelle@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:1678FC00-ACB8-46C8-835D-A96B496FA189@xxxxxxxxxxxxxxxx
Hello,
When there is a split task you can use your cursor to draw time worked
during the split by dragging your cursor along the timeline where the
split
occurs.
Is there a tool to do the oppsite of this. If you have a solid task and
you
want to quickly mark time not worked without changing the end date or
moving
any other splits that may exist later in the timeline?
Thanks,
Ellen
.
- Prev by Date: Re: Automatically change Gannt Bar Colour
- Next by Date: Re: Missing lines
- Previous by thread: Re: MS Project displaying cost information by task for each resource
- Next by thread: Re: Missing lines
- Index(es):
Relevant Pages
|