Re: Can you get work remaining as a time phased field in resource usag



Hi Dmatzy ,

Welcome to this Microsoft Project newsgroup :)

Try Inserting a new column for Remaining Work.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials

wrote:
I am using the default resource usage view and find it very helpful.
However, I noticed that I cannot find 'work remaining' in the list of
fields available to show as a time-phased field.

Is this available in some way? If not, is there a reason why? This
would be very helpful to have in the resource usage view. I could
use that field in this view to know how much remaining time I need
from each person on the plan by week and by month.

Now, the only remaining field I can get is 'remaining availability',
which is does not answer my question.



.