Re: Actual Work Moving



Hi Kurtis,

In the Resource Usage view, Insert the column for Remaining Work.

When I add Actual Work, in the Task Usage view, a few days before the task
should start, I get a warning to move the task start earlier or cancel. If
I select the start to move forward it re-adjusts the remaining work
spreading the original remaining hours. If I then add more Remianing Work,
it is spread again by lengthening the task.


Mike Glen
Project MVP



Temporalis wrote:
How can I enter the Remaining work on the "Task Usage" view?

I did figure out how to enter Remaining Work anyways (using the Entry
table), which does help. However, it doesn't resolve the problem I'm
having when I attempt to add actual work to the project before the
task start date.

Thanks,
- Kurtis Story



.



Relevant Pages

  • Re: How do I create a report with specifc columns in Project 2003?
    ... You might like to have a look at my series on Microsoft Project in the ... MS Project MVP ... >> with the assignment information, ... the only way to get that format is use the Resource Usage ...
    (microsoft.public.project)
  • Re: Resource Usage Reports
    ... You're welcome Marjorie and thanks for the feedback. ... Project MVP ... Visit http://project.mvps.org/ for the FAQs and additional information ... in the Resource Usage view, ...
    (microsoft.public.project)
  • Re: resource tasks
    ... Project MVP ... In the Resource Usage view, try inserting the project field if you ... can i print this king of lists? ...
    (microsoft.public.project)
  • Re: Unique Numbering in MSP Std
    ... IDs that are shown on the Resource Usage view. ... Project MVP ... On first appearance WBS looks ideal.... ...
    (microsoft.public.project)
  • Re: Project Split or Delay tasks
    ... Project MVP ... seems to be cleaner. ... usage view or the resource usage view. ... 75% after editing as it always shows the highest assignment unit. ...
    (microsoft.public.project)

Loading