Re: Actual Work Moving
- From: "Mike Glen" <glenATmvps.org>
- Date: Tue, 11 Apr 2006 10:50:37 +0100
Hi Kurtis,
In the Resource Usage view, Insert the column for Remaining Work.
When I add Actual Work, in the Task Usage view, a few days before the task
should start, I get a warning to move the task start earlier or cancel. If
I select the start to move forward it re-adjusts the remaining work
spreading the original remaining hours. If I then add more Remianing Work,
it is spread again by lengthening the task.
Mike Glen
Project MVP
Temporalis wrote:
How can I enter the Remaining work on the "Task Usage" view?
I did figure out how to enter Remaining Work anyways (using the Entry
table), which does help. However, it doesn't resolve the problem I'm
having when I attempt to add actual work to the project before the
task start date.
Thanks,
- Kurtis Story
.
- References:
- Actual Work Moving
- From: Temporalis
- Re: Actual Work Moving
- From: Mike Glen
- Re: Actual Work Moving
- From: Temporalis
- Actual Work Moving
- Prev by Date: Re: Email tasks to Generic Reources
- Next by Date: Re: Can you get work remaining as a time phased field in resource usag
- Previous by thread: Re: Actual Work Moving
- Next by thread: Re: Actual Work Moving
- Index(es):
Relevant Pages
|
Loading