Re: Email tasks to Generic Reources
- From: "Mike Glen" <glenATmvps.org>
- Date: Tue, 11 Apr 2006 10:26:39 +0100
Hi jms,
If you are using a server, try posting on the server newsgroup. Please see
FAQ Item: 24. Project Newsgroups. FAQs, companion products and other
useful Project information can be seen at this web address:
http://project.mvps.org/faqs.htm
Mike Glen
Project MVP
Rick Roszko wrote:
Generics act differently. E-mail won't work. Also, generic
assignemtns don't show up. Kinda annoying, I know.
Work around. Create a real, meaning, not generic, "plumber" in the MS
Project Resource pool through MS Project (never add resources through
the PWA interface!) as a MS Project Server resource, meaning, don't
add a Windows account. Add e-mail for that account. That account
should get e-mail.
Another hint. Don't have just one "plumber" (whether generic or
not). Have "plumber1", "plumber2", etc. Use these generics or
psuedo-reals as if it is a real person. When you do a "Replace" in
MS Project, all "plumber1" will go to that real resource. However,
if you have one plumber generic or psuedo-real, you'll have 50
ga-zillion hours on that one resouce which would be a nightmare to
figure out how to break out the task hours...
That work for you? If not, please re-post...
Thanks,
My user community wants to be able to assign a generic - like
plumber and have the task assingmenet request go to the manager of
the plumbers.... It appears that we can add an email address for
each generic resoruce , but the system will not mail the task
information to the email account that is listed.... Is this a set up
issue if not can it be changed another way ?
Thanks
.
- Prev by Date: Re: Is it possible to update progress manualy
- Next by Date: Re: Actual Work Moving
- Previous by thread: Re: What is C:\ProgramFiles\MicrosoftOffice\Office 10\WINWORD.EXE
- Next by thread: Re: Tasks of long duration contain w fews days actual work
- Index(es):
Relevant Pages
|