Hi,
Project is very poor at that. As you may see, many claim it is not necessary
(whereas it is a generally accepted practice in production environments);
maybe that is why the requests to develop it aren't honored.
Let's be positive: if you can fix the date at the end of the chain you can
use As Late As Possible constraints; if not you'll be condemned to make
manual adjustments, sorry:-(
--
Jan De Messemaeker, Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
For FAQs: http://www.mvps.org/project/faqs.htm
"stoods" <stoods@xxxxxxxxxxxxxxxxxxxxxxxxx> schreef in bericht
news:8CEAF96B-3907-4491-9BEB-E62E5C10406A@xxxxxxxxxxxxxxxx
Hi,figure
Project is doing a great job of levelling teh resources, but I cannot
out how to get project to just in time various tasks. It is currentlymoveing
tasks with a start as soon as possible, but it I want to delay these taskslevel
until they are closer to the last task in a group of tasks. Ie, task 1 is
followed by task2 which is followed on by task 4 and so on. How can I
so that the start of task 1 minimises time between task 1 and task 4?
Thanks,
Mike
.
- Prev by Date: Re: Just in Time levelling
- Next by Date: Re: changing a task finish date
- Previous by thread: Re: Just in Time levelling
- Next by thread: Re: Just in Time levelling
- Index(es):
Relevant Pages
|