Re: Just in Time levelling
- From: "Rod Gill" <rod AT project-systems DOT co DOT nz>
- Date: Wed, 5 Apr 2006 18:29:56 +1200
Are you sure you want to do that? If all tasks start as late as possible,
then they are all critical. Delaying any task delays the project finish
date.
--
Rod Gill
Project MVP
Visit www.msproject-systems.com for Project Companion Tools and more
"stoods" <stoods@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:8CEAF96B-3907-4491-9BEB-E62E5C10406A@xxxxxxxxxxxxxxxx
Hi,
Project is doing a great job of levelling teh resources, but I cannot
figure
out how to get project to just in time various tasks. It is currently
moveing
tasks with a start as soon as possible, but it I want to delay these tasks
until they are closer to the last task in a group of tasks. Ie, task 1 is
followed by task2 which is followed on by task 4 and so on. How can I
level
so that the start of task 1 minimises time between task 1 and task 4?
Thanks,
Mike
.
- Prev by Date: Re: how do I change the size of the boxes in the network diagram
- Next by Date: Re: Just in Time levelling
- Previous by thread: Re: how do I change the size of the boxes in the network diagram
- Next by thread: Re: Just in Time levelling
- Index(es):