Re: % Complete, actual finish dates, and predecessors



For my purposes, I'm not tracking the percentage complete as a progressive
number. Instead I'm treating it as a boolean - either the task is finished
or it isn't. It's more important to me that the future start dates that are
linked to the finished task update accordingly.

I think the easist way for me to do this is to not touch the percentage
complete at all, but to first save a baseline and then adjust the actual
finish dates on each task as it is complete. That way if I'm entering
today's date, the percentage complete records as 100% and the following start
dates change properly (so I won't have to also adjust the actual start date,
it will do it automatically).

Thanks for your response!!



"Rod Gill" wrote:

When you set 100% complete, Project copies the Start and Finish dates and
puts them to Actual Start and Actual Finish. The better way to update with %
complete is to apply the Tracking Table (View, Table) then:
1) Enter the Actual Start Date
2) Enter Actual Duration so far
3) Enter new remaining duration (0=complete)

Experiment with these. If you have saved a baseline first then the Tracking
Gantt chart will show progress.

--

Rod Gill
Project MVP
Visit www.msproject-systems.com for Project Companion Tools and more


"Dena" <Dena@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:01839F4A-77BA-4953-9C3D-09A225F20800@xxxxxxxxxxxxxxxx
I'm having trouble getting Project to properly update my start and finish
dates when I set a task to 100% complete. I've set up my gantt chart view
to
show columns for percent complete and actual finish dates. In my Project
training course, I was told that if I set a task to 100% complete, Project
would automatically assume today's date as the actual finish date, but
this
is not happening. Instead the actual finish date is being recorded as the
regular finish date that was first estimated. I want it to automatically
record the current calendar date as the actual finish date when I set a
task
to 100% complete.

I also want the start date of the task that is being set to 100% complete
to
remain fixed, and the duration to adjust accordingly. THEN I want the
start
dates of all subsequent linked tasks to update based on the actual finish
date of the predecessor.

Can someone help me with this? If this is not possible with Project as it
comes, perhaps there is a script that can do this?




.

.



Relevant Pages

  • Re: Tracking a schedule: best practices
    ... Show the Tracking Gantt Ciew ... Remaining Duration. ... You see many Gantt Charts with both unused Duration in the past and progress ... or ahead of schedule? ...
    (microsoft.public.project)
  • Re: Adjusting remaining duration of task does not auto-adjust link
    ... If you show any progress on Task 2 its start date is locked in granite and nothing will change it. ... "% Complete" entries represent actual historical fact as far as Project is concerned and the only way any progress can occur is for a resource to do some physical action. ... The only time the successor's start date would change in response to a revision of the predecessor's duration is if its progress is still 0%. ... >> * Adjust first task remaining duration to add one more day ...
    (microsoft.public.project)
  • Re: % complete of a task moving back to before todays date
    ... why not just use that hard data (ie facts). ... Also, in my experience, many progress tracking problems stem from people ... of the Duration that has elapsed. ...
    (microsoft.public.project)
  • Re: Progress Lines
    ... for tracking is to firstly save a baseline. ... then enter actual duration and remaining duration ... A progress line would therefore be on the status date. ...
    (microsoft.public.project)
  • Re: help
    ... % Complete refers to available working time elapsed so far versus total project duration. ... % Physical Complete is an estimate of the amount of deliverable completed versus the amount required ... demanded msproject) the progress is not quite 70%. ... Then switch to the tracking table and tracking Gantt views, ...
    (microsoft.public.project)