Re: Sorting in Resource Usage View
- From: "JulieS" <passport6847 at maine dot rr dot com>
- Date: Tue, 21 Mar 2006 18:08:21 -0500
Hi SFSailLady,
I believe the difficulty you are having is because the "Start" field in the
resource Usage view is the start for the Resource, not the start for the
assignments. See FAQ #51 at:
http://project.mvps.org/faqs.htm
for additional details.
You may have better luck using grouping than sorting as grouping would allow
you to group by Name (resource field) then Start date (assignment field).
I hope this helps. Let us know how you get along.
Julie
"SFSailLady" <SFSailLady@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:1EECEB78-F641-46EE-B8AA-12593ABC0BA3@xxxxxxxxxxxxxxxx
I think you misunderstood the question. Sort by "Start" then rearranges
the
"names" even if they were sorted first. I don't want that. I want the
names
sorted, then for the tasks under that name, I want the tasks sorted by
"Start". So, the final view should have names sorted and within each
name,
tasks sorted by Start.
"Rick Roszko" wrote:
Do a sort by "Name" by that column only.
(only have sort on "Name", leave the other two blank)
Next do a sort by "Start"
(only have sort on "Start", leave the other two blank)
--
Rick Roszko
PM, MSPS, Network Consultant
"SFSailLady" wrote:
OK, I feel stupid. I can't seem to get the Resource Usage view to sort
the
way I want it to. My columns are: Info, Resource Name, Task Outline
Number,
Start, FInish, and Work. I want to sort by 'name' and then by 'start'.
I do
sort by 'name' and then sort by 'start'. It only sorts by name. What
am I
doing wrong?
Just to be 100% precise, the steps I do are right-click on Resource
Name
column, Sort By..., and then in sort dialog choose 'name' and then
'start'.
Help. Thanks.
.
- Follow-Ups:
- Re: Sorting in Resource Usage View
- From: John
- Re: Sorting in Resource Usage View
- From: SFSailLady
- Re: Sorting in Resource Usage View
- Prev by Date: Re: Gantt Chart Display = Progress against plan
- Next by Date: Re: Sorting in Resource Usage View
- Previous by thread: Re: Gantt Chart Display = Progress against plan
- Next by thread: Re: Sorting in Resource Usage View
- Index(es):
Relevant Pages
|