Re: It's all in the Leveling(?)



Hi,

Recurring tasks are a very very good solution.
"Open" the summary tasks to show the details, Insert the priority column and
change away from 1000 as desired.

As for grouping the tasks, except maybe manually playing around with
priorities, the only solution I see is a VBA procedure to be run before
leveling, where tasks from a started summary task automatically get a high
priority.

Hope this helps

--
Jan De Messemaeker, Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
For FAQs: http://www.mvps.org/project/faqs.htm
"Beyers Konig" <BeyersKonig@xxxxxxxxxxxxxxxxxxxxxxxxx> schreef in bericht
news:C8083BCD-A769-4639-9733-E3E1D07A4397@xxxxxxxxxxxxxxxx
Hi

I have to manage 11 projects using about 14 resources. Each project
contains
about 200 tasks, giving a total of more than 1500 tasks. I use Project
Professional 2003 with its Enterprise features. The Resources enter actual
work done on Project Web interface. I use only Enterprise Resources and
have
created one Global Masterproject where all the other projects are inserted
as
'sub-projects' into this master project.

The projects range from Hardware, Firmware and Software Development to
Production planning and Installation Management. Because of the amount of
projects running concurrently I have to use Resource Leveling, but major
limitations in the way it works makes it virtually impossible for me to
use.

The problems I am facing is this: (Keep in mind I have to use Priorities
as
our featurelist and feature priorities are very dynamic)

A) How to handle what I call 'Monitor Tasks'.
To explain: Say for instance we order our BOM. The orders for the hundreds
of components are placed at various companies. After order placement,
somebody has to track the progress of order delivary. Thus the task would
be
"Monitor/Track Order Delivery Progress". Now, the resource doing the
tracking
needs a variable amount of time each day of say 1 to 2 hrs each day. This
resource hours must of course be taken into account in Project Planning.
i) If I use a Task where the resource units are entered a say 12%
(about 1hr/day) then 'Resource Leveling...' moves task with 100% allocated
units out and does a bad job of overlapping other less than 100% unit
tasks
for the same resource. (I can allow for splitting of task only for certain
tasks, but not for all tasks throughout, i.e. I cannot split a code
development task, and Project does not allow me to specifay which tasks
can
be split and which not)
ii) If I use a "Recurring Task" then I run into the problem that
these tasks have priorities of 1000 and I cannot level

B) Our development are done on a feature by feature basis. Every feature
has
a number of tasks to complete that feature. I want to Prioritise and Plan
the
development of these features (by using "resource Leveling"). When work on
a
feature starts then all the (sub)tasks for that feature must be carried
out,
without delay between these tasks or splitting of these tasks, untill all
work on the feature is done. Thus, "Resource Leveleing must "move" (or
delay)
features (which in essence is a summary task) rather than moving the tasks
themselves. Another way of saying this is: Project must allow me to
'group'
tasks, and then thes groupings will be prioritised and moved/delayed in
order
to Level the Resource allocations. (Note: There are not (normally)
depandancies between the tasks of different features)

I have found no way Project can do this.
I hope someone can help.
Thanks
Beyers


.



Relevant Pages

  • Re: Its all in the Leveling(?)
    ... companion products and other useful Project information ... amount of projects running concurrently I have to use Resource ... Priorities as our featurelist and feature priorities are very dynamic) ... Our development are done on a feature by feature basis. ...
    (microsoft.public.project)
  • Re: Its all in the Leveling(?)
    ... companion products and other useful ... Priorities as our featurelist and feature priorities are very dynamic) ... resource doing the tracking needs a variable amount of time each day ... Our development are done on a feature by feature basis. ...
    (microsoft.public.project.pro_and_server)
  • Its all in the Leveling(?)
    ... Priorities as our featurelist and feature priorities are very dynamic) ... resource doing the tracking needs a variable amount of time each day of ... Our development are done on a feature by feature basis. ... these tasks or splitting of these tasks, untill all work on the feature ...
    (microsoft.public.project.pro_and_server)
  • Its all in the Leveling
    ... Priorities as our featurelist and feature priorities are very dynamic) ... resource doing the tracking needs a variable amount of time each day of ... Our development are done on a feature by feature basis. ... these tasks or splitting of these tasks, untill all work on the feature ...
    (microsoft.public.project.pro_and_server)
  • Re: MS Project Integration with Outlook
    ... I have not used the workgroup feature in Project 2003, ... If I recall correctly, when the resource updates ... Please see the following Knowledge Base article: ...
    (microsoft.public.project)