Re: It's all in the Leveling(?)
- From: "Jan De Messemaeker" <jandemes at prom hyphen ade dot be>
- Date: Mon, 20 Mar 2006 18:45:52 +0100
Hi,
Recurring tasks are a very very good solution.
"Open" the summary tasks to show the details, Insert the priority column and
change away from 1000 as desired.
As for grouping the tasks, except maybe manually playing around with
priorities, the only solution I see is a VBA procedure to be run before
leveling, where tasks from a started summary task automatically get a high
priority.
Hope this helps
--
Jan De Messemaeker, Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
For FAQs: http://www.mvps.org/project/faqs.htm
"Beyers Konig" <BeyersKonig@xxxxxxxxxxxxxxxxxxxxxxxxx> schreef in bericht
news:C8083BCD-A769-4639-9733-E3E1D07A4397@xxxxxxxxxxxxxxxx
Hicontains
I have to manage 11 projects using about 14 resources. Each project
about 200 tasks, giving a total of more than 1500 tasks. I use Projecthave
Professional 2003 with its Enterprise features. The Resources enter actual
work done on Project Web interface. I use only Enterprise Resources and
created one Global Masterproject where all the other projects are insertedas
'sub-projects' into this master project.use.
The projects range from Hardware, Firmware and Software Development to
Production planning and Installation Management. Because of the amount of
projects running concurrently I have to use Resource Leveling, but major
limitations in the way it works makes it virtually impossible for me to
as
The problems I am facing is this: (Keep in mind I have to use Priorities
our featurelist and feature priorities are very dynamic)be
A) How to handle what I call 'Monitor Tasks'.
To explain: Say for instance we order our BOM. The orders for the hundreds
of components are placed at various companies. After order placement,
somebody has to track the progress of order delivary. Thus the task would
"Monitor/Track Order Delivery Progress". Now, the resource doing thetracking
needs a variable amount of time each day of say 1 to 2 hrs each day. Thistasks
resource hours must of course be taken into account in Project Planning.
i) If I use a Task where the resource units are entered a say 12%
(about 1hr/day) then 'Resource Leveling...' moves task with 100% allocated
units out and does a bad job of overlapping other less than 100% unit
for the same resource. (I can allow for splitting of task only for certaincan
tasks, but not for all tasks throughout, i.e. I cannot split a code
development task, and Project does not allow me to specifay which tasks
be split and which not)has
ii) If I use a "Recurring Task" then I run into the problem that
these tasks have priorities of 1000 and I cannot level
B) Our development are done on a feature by feature basis. Every feature
a number of tasks to complete that feature. I want to Prioritise and Planthe
development of these features (by using "resource Leveling"). When work ona
feature starts then all the (sub)tasks for that feature must be carriedout,
without delay between these tasks or splitting of these tasks, untill alldelay)
work on the feature is done. Thus, "Resource Leveleing must "move" (or
features (which in essence is a summary task) rather than moving the tasks'group'
themselves. Another way of saying this is: Project must allow me to
tasks, and then thes groupings will be prioritised and moved/delayed inorder
to Level the Resource allocations. (Note: There are not (normally)
depandancies between the tasks of different features)
I have found no way Project can do this.
I hope someone can help.
Thanks
Beyers
.
- Follow-Ups:
- Re: It's all in the Leveling(?)
- From: Beyers Konig
- Re: It's all in the Leveling(?)
- Prev by Date: Re: Leveling - to use or not?
- Next by Date: Re: Resource Hours Showing in Resource Pool
- Previous by thread: Re: It's all in the Leveling(?)
- Next by thread: Re: It's all in the Leveling(?)
- Index(es):
Relevant Pages
|