Re: Project Summary Task Durations



Hi,

Rollup of durations is calculating the difference between first start and
last finish.
If there are two tasks tomorrow, each during one day, total duration of the
two is only tomorrow, be it one day.
Work on the other hand is a scalar and totalled by Project.
Hoiep this helps,

--
Jan De Messemaeker, Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
For FAQs: http://www.mvps.org/project/faqs.htm
"Mary Beth" <MaryBeth@xxxxxxxxxxxxxxxxxxxxxxxxx> schreef in bericht
news:CCC643EF-3764-4414-955B-F950DC452F09@xxxxxxxxxxxxxxxx
I have a project plan that was started from scratch. I have the normal
Summary tasks followed by subtasks. I have entered all of my subtask
duration but the plan is not 'rolling up' those durations for me and
calculating my summary task durations. is there a setting I need to make
to
make this roll-up happen?


.



Relevant Pages

  • Re: Predecessors and durations
    ... Visit http://project.mvps.org/ for the FAQs and additional information ... entered durations for the tasks. ... Project *should* be calculating the start dates and ...
    (microsoft.public.project)
  • Re: Predecessors and durations
    ... It looks like Steve has given you a very plausible explaination for the ... entered durations for the tasks. ... Project *should* be calculating the start dates and ...
    (microsoft.public.project)
  • Re: Predecessors and durations
    ... Visit http://project.mvps.org/ for the FAQs and additional information ... entered durations for the tasks. ... Project *should* be calculating the start dates and ...
    (microsoft.public.project)
  • Re: Date problem...
    ... Project is designed to show you what is possible to achieve by calculating ... the critical path from the Durations and Precedence logic links and resource ... as the possible dates do not meet the deadlines, ... >>Basically it does sophisticated date math. ...
    (microsoft.public.project)
  • durations problem?
    ... i have problem with durations ... but while i change them the summary tasks are ... in week & subtasks in day & when i change them to week ...
    (microsoft.public.project.standard_and_server)