Re: Inserting a Time Scale



In article <AD804AE8-B164-4142-BC73-8F06C0790D9C@xxxxxxxxxxxxx>,
Michael <Michael@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote:

Hello,
My new boss loves the new MS Project Gantt chart I presented. However, he
would like to see the timescale at the top of the page inserted in the chart
in two spots, above summary tasks. Is this possible?

Michael,
I'm not sure I understand what you mean by "two spots, above the summary
tasks", but Project only has one timescale, although there are up to
three tiers (e.g. Year, month, week). Project doesn't have an extensive
amount of graphics capability. If you need custom presentations, you
will need to export Project's data to another application and create the
view there.

John
Project MVP
.