Re: Printing Bar Text
- From: John <mjensen@xxxxxxxxxxxx>
- Date: Fri, 24 Feb 2006 09:20:02 -0700
In article <17A20C94-C6BE-41E9-9A49-654F59DAAC75@xxxxxxxxxxxxx>,
"Peter J" <Peter J@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote:
I have a project file with about two hundred activities.
One of the bar formats I have defined has bar text to the right of the bar.
The text field used is text2.
When printed or previewed for print, the text on the first bar of each page
is some little way to the right of the bar where as others are right next to
the bar.
In the working view it is fine.
Peter,
My first guess is that there are leading spaces ahead of the text in
Text2 for that task. You may not notice them when you view the field
itself but they will definitely leave a space on the Gantt display.
John
Project MVP
.
- Prev by Date: Re: ressource report sorted by deadline
- Next by Date: Re: Odd Start Date
- Previous by thread: Re: ressource report sorted by deadline
- Next by thread: Re: Printing Bar Text
- Index(es):
Relevant Pages
|
Loading