Re: Earned Value Analysis (EVA) graphing from Project Prof



Exporting with the Analyse Timescaled Data... tool in Project will create an Excel work*** with the necessary data. Then in Excel use the graphing tools to create your curves and use regression analysis to extend them to predcit the finish date and finish actual cost.

--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs

"Nock" <Nock@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message news:C6021BED-7EAD-4374-AC86-6BBC850D95CE@xxxxxxxxxxxxxxxx
Hi all,

Q. How can you generate EVA based graphs in Excel (2003) from Project 2003
data? I know you can use the 'Analyse Timescaled Data in Excel' from within
Project Professional but I can't get a generic 'time' vs 'cost' view
(with a predicted project finish point).

Also, if you can do this, is it possible to script or code the process?

Many thanks,

Nock



.