Re: baseline vs actual task report



Take a look at the Tracking Table in the Gantt chart view - if you add columns for the Baseline Start and Baseline Finish what do you need that's not listed there? Or perhaps a custom table showing Base and Actual starts and finishes. (The Actual fileds are blank for work that has not yet been done.) Or a thrid option is to substitute the Actual Start and Actual Finish fields for the plain Start and Finish fields in a copy of the variance table.

BTW, the stock variance report is not showing "actual future dates." It's showing Actual Dates for work that has been done and *forecast* dates for work that has not been done.
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


"Carey" <Carey@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message news:B9769492-1D67-4B36-8E17-A78E73DA6458@xxxxxxxxxxxxxxxx
Steve, I agree. However, MS Project 2003 produces the actual future dates in
the variance report. Do you know of a report that will give me only the
actual dates that have passed? Your comment does not answer my question. I
want to be able to produce a report that shows the base line start and finish
dates and the actual dates that have transpired for all task but leave the
actual dates that have not transpired blank. Any help you can provide will
be appreciated.

Carey

"Steve House [Project MVP]" wrote:

How can there be "actual future dates?" An actual date is one that has
actually transpired and unless you have a time machine that cannot be in the
future. Things that have happened are actuals. Things that haven't
happened are forecasts.
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs



"Carey" <Carey@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:29783BC0-A207-4E5A-9A0C-9357A53B0165@xxxxxxxxxxxxxxxx
>I would like to generate a report with baseline dates vs actual dates.
> However, I do not want to see the actual future dates if the start date
> has
> not occurred. Whick report can use that will give me that information
> along
> with the gant chart?



.



Relevant Pages

  • Re: BCWP and BCWS
    ... only value showing is under costs. ... By using actual and remaining duration, ... No you shouldn't save a new baseline. ... report with the existing baseline. ...
    (microsoft.public.project)
  • Re: Rowsource of unbound object
    ... That is because the Format function returns a string. ... This works in a query, not sure how it will work for your Gantt Chart ... The report events are Open, Close, Activate, Deactivate, No Data, ...
    (microsoft.public.access.modulesdaovba)
  • Re: placing textfields in a specific place
    ... I took your advice and played around with the report... ... I am trying to produce a kind of Gantt chart on a form. ... Dim lngOneMinute As Long 'size of one minute in twips ... Dim datSchedStart As Date ...
    (microsoft.public.access.formscoding)
  • Re: BCWP and BCWS
    ... You have resources without costs assigned to tasks ... Single click Earned Value over Time Report ... By using actual and remaining duration, ... No you shouldn't save a new baseline. ...
    (microsoft.public.project)
  • Re: BCWP and BCWS
    ... You have resources without costs assigned to tasks ... Single click Earned Value over Time Report ... By using actual and remaining duration, ... No you shouldn't save a new baseline. ...
    (microsoft.public.project)