Re: Effort driven fixed duration task

Tech-Archive recommends: Repair Windows Errors & Optimize Windows Performance



Thank you Mike for your reply.


"Mike Glen" ha scritto:

> Hi Michele,
>
> Welcome to this Microsoft Project newsgroup :)
>
> You need to make the Task Type Fixed Work to achieve what you want.
>
> You might like to have a look at my series on Microsoft Project in the
> TechTrax ezine, particularly #11 on Task Types, at this site:
> http://tinyurl.com/2xbhc or this:
> http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
> (Perhaps you'd care to rate the article before leaving the site, :)
> Thanks.)
>
> FAQs, companion products and other useful Project information can be seen at
> this web address: http://project.mvps.org/faqs.htm
>
> Hope this helps - please let us know how you get on :)
>
> Mike Glen
> MS Project MVP
>
> Michele wrote:
> > I have a fixed duration effort driven task with one resource
> > assigned.(2 days of duration and 8 hours of work)
> > I want to create another assignment for the same task, but with an
> > amount of work equal to 2 hours so that the first assignment need to
> > work only for 6 hours.
> > (that's what i understand about the definition of effort driven task)
> > I know i can do that manually using the bottom pane of any of the
> > tasks views split window and digiting 2 hours of work for the second
> > assignment and 8 hours for the first but, in my opinion, there
> > should be the possibility to associate to the second assignment, as
> > soon as you're creating it, 2 hours of work and Project should than
> > calculate the remaining work of 6 hours for the first assignment.(If
> > i create the second assignment in a window split and i digit 2 hours
> > of work without changing the work hours of the first assignment, the
> > total amount of work becomes 10 hours and not 8 like it should be
> > since the task is effort driven!!!!)
> > Why isn't that possible, and if it is how can i achieve that?
> > Really Thanks a lot
> > Michele
>
>
>
>
.



Relevant Pages

  • Re: Effort driven fixed duration task
    ... You're welcome, Michele :-) ... >> MS Project MVP ... >>> amount of work equal to 2 hours so that the first assignment need to ...
    (microsoft.public.project)
  • Re: Effort driven fixed duration task
    ... You need to make the Task Type Fixed Work to achieve what you want. ... You might like to have a look at my series on Microsoft Project in the ... > amount of work equal to 2 hours so that the first assignment need to ...
    (microsoft.public.project)
  • Re: Task Type - Developing versus Track the Schedule
    ... When creating an Assignment, the Task Type does nothing! ... EG have 20h more work but task mustn't take any longer, so edit the work to add 20h, fix Duration then Units gets recalculated to show the new availability you need. ... I do this to DEVELOP my schedule. ...
    (microsoft.public.project)
  • Re: Urgent : Duration getting automatically changed
    ... A task type of Fixed Duration DOES NOT mean that the duration is engraved in granite and will never change under any circumstance, nor does it mean it's read-only and cannot be edited. ... It means that when you have a resource assigned and edit one of the assignment parameters so as to change either the work performed by the resource or the effort units he's assigned to work, the duration will remain constant and the either the units will change or the work will change. ...
    (microsoft.public.project)
  • Re: Writing the breakout novel
    ... stimulate their imagination. ... I've noted it in my course calendar for the next presentation. ... time they have to do the first assignment. ...
    (rec.arts.sf.composition)