Re: Effort driven fixed duration task

Tech-Archive recommends: Repair Windows Errors & Optimize Windows Performance



Hi Michele,

Welcome to this Microsoft Project newsgroup :)

You need to make the Task Type Fixed Work to achieve what you want.

You might like to have a look at my series on Microsoft Project in the
TechTrax ezine, particularly #11 on Task Types, at this site:
http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the article before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP

Michele wrote:
> I have a fixed duration effort driven task with one resource
> assigned.(2 days of duration and 8 hours of work)
> I want to create another assignment for the same task, but with an
> amount of work equal to 2 hours so that the first assignment need to
> work only for 6 hours.
> (that's what i understand about the definition of effort driven task)
> I know i can do that manually using the bottom pane of any of the
> tasks views split window and digiting 2 hours of work for the second
> assignment and 8 hours for the first but, in my opinion, there
> should be the possibility to associate to the second assignment, as
> soon as you're creating it, 2 hours of work and Project should than
> calculate the remaining work of 6 hours for the first assignment.(If
> i create the second assignment in a window split and i digit 2 hours
> of work without changing the work hours of the first assignment, the
> total amount of work becomes 10 hours and not 8 like it should be
> since the task is effort driven!!!!)
> Why isn't that possible, and if it is how can i achieve that?
> Really Thanks a lot
> Michele



.



Relevant Pages

  • Re: Effort driven fixed duration task
    ... > Hi Michele, ... > You need to make the Task Type Fixed Work to achieve what you want. ... >> amount of work equal to 2 hours so that the first assignment need to ...
    (microsoft.public.project)
  • Re: Break the link betweek duration and work.
    ... If you change duration of this fixed duration task to 5 days, ... about Microsoft Project ... If you change duration - work will change to accomodate the assignment ... You can change tasks type is two places: Window/Split and the Task Type ...
    (microsoft.public.project)
  • Re: Cannot get divided Work to reflect Assignment Unit percentage
    ... > I tried your suggestion to use the Task Usage View and add the Assignment ... >> You can enter both Assignment Units and Work on ... >> Microsoft Project Most Valuable Professional ... Now I am assigning resources. ...
    (microsoft.public.project)
  • Re: Task splitting - a process, not a parameter?
    ... Jan De Messemaeker ... Microsoft Project Most Valuable Professional ... This is to check my understanding from observation of how task ... > zeroing out a resource's work in the middle of a task assignment and ...
    (microsoft.public.project)
  • Re: Task Type - Developing versus Track the Schedule
    ... When creating an Assignment, the Task Type does nothing! ... EG have 20h more work but task mustn't take any longer, so edit the work to add 20h, fix Duration then Units gets recalculated to show the new availability you need. ... I do this to DEVELOP my schedule. ...
    (microsoft.public.project)