Re: Creating S curve graph with days management
- From: "davegb" <davegb@xxxxxxxxxxxxxx>
- Date: 4 Jan 2006 07:00:14 -0800
martin.champoux@xxxxxxxxx wrote:
> Hello,
>
> I'm would like to create a S curve graph but we don't manage the cost
> of the project at my level, only the number of days per task. Number of
> days for each task and the number of days worked.
>
> How can I create the graph ?
>
> How can I switch from money caculation to days ?
>
> I saw calculation formula in the help file but It was with the Cost
> budget and Cost worked.
>
> Thanks in advance
>
> Marty
I've seen S curves done on many different variables, including
variations on cost (capital cost usually doesn't work because it can
fluctuate so much month to month, gives a jagged S curve), yds of
concrete, metric tons of structural steel or rebar, etc. And on
manhours. I'd suggest you base yours on manhours of labor. Others might
have equally valuable suggestions.
To get the S curve, you need to get a view in Project showing manhours,
then copy and paste the data into Excel (a copy, Paste Special, Paste
Link will hotlink the data), then create your graph.
Hope this helps in your world.
.
- References:
- Creating S curve graph with days management
- From: martin . champoux
- Creating S curve graph with days management
- Prev by Date: Re: Project and Access
- Next by Date: Re: Will Project Work For Us?
- Previous by thread: Creating S curve graph with days management
- Next by thread: Re: Creating S curve graph with days management
- Index(es):
Relevant Pages
|