Re: vertical bars in gantt view (MS Project)
- From: "Jan De Messemaeker" <jandemes at prom hyphen ade dot be>
- Date: Thu, 29 Dec 2005 17:11:47 +0100
Hi,
You will only see the bar for whole multiples of the minor timescale. Make
that days (if necessary iuse three scale and put the scale to very low).
HTH
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"Heather" <Heather@xxxxxxxxxxxxxxxxxxxxxxxxx> schreef in bericht
news:2F99DFFC-7007-483D-BF8F-8C696A37E915@xxxxxxxxxxxxxxxx
> Jan,
>
> Extremely helpful - I learned something new today. However, Project is
only
> showing the nonworking time for whole months versus showing the nonworking
> time that spans from mid-month to the next mid-month (ex: 9 Jan to 8 Feb).
> It's a 30 day period but it's over two months. Now if I change the
> nonworking time to 1 Jan to 31 Jan - the veritcal bar appears. Any
> suggestions? I've been messing with the timescale but can't figure it
out.
> Thanks Jan!
>
> "Jan De Messemaeker" wrote:
>
> > Hi,
> >
> > I interpreted "bar" as "line"
> > To show the nonworking bar is just as soimple, no macro required.
> > Create a new calendar as a copy of the project calendar (Tools, Cghabge
> > Working time, New)
> > In that calendar set the interruption as nonworking time
> > Now in Format, Timescalee, nonworking time, select teh new calendar.
> > I dearly love and adore VBA but there isn't always a need for it!
> > HTH
> >
> > --
> > Jan De Messemaeker
> > Microsoft Project Most Valuable Professional
> > http://users.online.be/prom-ade/
> > +32-495-300 620
> > "Heather" <Heather@xxxxxxxxxxxxxxxxxxxxxxxxx> schreef in bericht
> > news:6AF75B19-C92E-4BA9-8E42-64E3284247F4@xxxxxxxxxxxxxxxx
> > > Jan,
> > >
> > > Yes, the date range question is the same. I just wanted to know how
to
> > > change the status date because I do use the gridlines.
> > >
> > > Essentially in my schedule, I have an event of 30+days in duration
that
> > > requires no other work to be done during that event's duration so I
wanted
> > to
> > > visually block out that time throughout the whole schedule - with a
> > vertical
> > > bar during the duration of the event. The scheduling team I worked
with a
> > > few years ago was able to do this but as I recall it was the result of
> > > running a macro. I wanted to try to get the vertical bars in the
gantt
> > view
> > > without running a macro. Thanks!
> > >
> > > "Jan De Messemaeker" wrote:
> > >
> > > > Hi,
> > > >
> > > > The status date can be set in Project, Project Information.
> > > > Your date range problem is not the same question is it?
> > > >
> > > > --
> > > > Jan De Messemaeker
> > > > Microsoft Project Most Valuable Professional
> > > > http://users.online.be/prom-ade/
> > > > +32-495-300 620
> > > > "Heather" <Heather@xxxxxxxxxxxxxxxxxxxxxxxxx> schreef in bericht
> > > > news:9E9151AC-6CA5-4B95-B309-6B95DD8FE0B0@xxxxxxxxxxxxxxxx
> > > > > Hi Jan -
> > > > >
> > > > > Thanks for the response. How do you change the date for the
status
> > line?
> > > > > Also I'm needing a date range versus one day. I think I'm going
to
> > have
> > > > to
> > > > > learn macros.
> > > > >
> > > > > "Jan De Messemaeker" wrote:
> > > > >
> > > > > > Hi Heather,
> > > > > >
> > > > > > Through Format, Gridlines, you can define some vertical
linessuch as
> > for
> > > > > > Project Start or Status Date; if you do not use the status date
for
> > > > other
> > > > > > purposes, you can set it at any date you want to draw the
vertical
> > line
> > > > you
> > > > > > want.
> > > > > >
> > > > > > --
> > > > > > Jan De Messemaeker
> > > > > > Microsoft Project Most Valuable Professional
> > > > > > http://users.online.be/prom-ade/
> > > > > > +32-495-300 620
> > > > > > "Heather" <Heather@xxxxxxxxxxxxxxxxxxxxxxxxx> schreef in bericht
> > > > > > news:692A90B3-3E46-4FA4-97BD-AA0D25134F23@xxxxxxxxxxxxxxxx
> > > > > > > I've worked with Project for three years now, and recall that
you
> > can
> > > > add
> > > > > > > vertical bars in the gantt view to highlight the duration of
an
> > event
> > > > > > > throughout the entire file (helps to highlight possible
conflict
> > > > areas).
> > > > > > I
> > > > > > > cannot recall if it can be done without writing a macro. I
> > believe
> > > > when I
> > > > > > > worked with it before the vertical bars came through after
running
> > a
> > > > > > macro.
> > > > > > > But if it can be done without running a macro, I would prefer
to
> > do
> > > > that.
> > > > > >
> > > > > >
> > > > > >
> > > >
> > > >
> > > >
> >
> >
> >
.
- References:
- Re: vertical bars in gantt view (MS Project)
- From: Jan De Messemaeker
- Re: vertical bars in gantt view (MS Project)
- From: Jan De Messemaeker
- Re: vertical bars in gantt view (MS Project)
- From: Heather
- Re: vertical bars in gantt view (MS Project)
- From: Jan De Messemaeker
- Re: vertical bars in gantt view (MS Project)
- From: Heather
- Re: vertical bars in gantt view (MS Project)
- Prev by Date: Re: relative path to shared resource file
- Next by Date: Re: vertical bars in gantt view (MS Project)
- Previous by thread: Re: vertical bars in gantt view (MS Project)
- Next by thread: Re: Master Project / Resource Usage Gantt
- Index(es):
Relevant Pages
|