Re: vertical bars in gantt view (MS Project)
- From: "Heather" <Heather@xxxxxxxxxxxxxxxxxxxxxxxxx>
- Date: Wed, 28 Dec 2005 14:46:02 -0800
Jan - I did get it to work but now because I put days as the minor time scale
it's showing all the weekends - do you know how to change it so it doesn't
show the weekends as nonworking time? Thanks!
"Heather" wrote:
> Jan,
>
> Extremely helpful - I learned something new today. However, Project is only
> showing the nonworking time for whole months versus showing the nonworking
> time that spans from mid-month to the next mid-month (ex: 9 Jan to 8 Feb).
> It's a 30 day period but it's over two months. Now if I change the
> nonworking time to 1 Jan to 31 Jan - the veritcal bar appears. Any
> suggestions? I've been messing with the timescale but can't figure it out.
> Thanks Jan!
>
> "Jan De Messemaeker" wrote:
>
> > Hi,
> >
> > I interpreted "bar" as "line"
> > To show the nonworking bar is just as soimple, no macro required.
> > Create a new calendar as a copy of the project calendar (Tools, Cghabge
> > Working time, New)
> > In that calendar set the interruption as nonworking time
> > Now in Format, Timescalee, nonworking time, select teh new calendar.
> > I dearly love and adore VBA but there isn't always a need for it!
> > HTH
> >
> > --
> > Jan De Messemaeker
> > Microsoft Project Most Valuable Professional
> > http://users.online.be/prom-ade/
> > +32-495-300 620
> > "Heather" <Heather@xxxxxxxxxxxxxxxxxxxxxxxxx> schreef in bericht
> > news:6AF75B19-C92E-4BA9-8E42-64E3284247F4@xxxxxxxxxxxxxxxx
> > > Jan,
> > >
> > > Yes, the date range question is the same. I just wanted to know how to
> > > change the status date because I do use the gridlines.
> > >
> > > Essentially in my schedule, I have an event of 30+days in duration that
> > > requires no other work to be done during that event's duration so I wanted
> > to
> > > visually block out that time throughout the whole schedule - with a
> > vertical
> > > bar during the duration of the event. The scheduling team I worked with a
> > > few years ago was able to do this but as I recall it was the result of
> > > running a macro. I wanted to try to get the vertical bars in the gantt
> > view
> > > without running a macro. Thanks!
> > >
> > > "Jan De Messemaeker" wrote:
> > >
> > > > Hi,
> > > >
> > > > The status date can be set in Project, Project Information.
> > > > Your date range problem is not the same question is it?
> > > >
> > > > --
> > > > Jan De Messemaeker
> > > > Microsoft Project Most Valuable Professional
> > > > http://users.online.be/prom-ade/
> > > > +32-495-300 620
> > > > "Heather" <Heather@xxxxxxxxxxxxxxxxxxxxxxxxx> schreef in bericht
> > > > news:9E9151AC-6CA5-4B95-B309-6B95DD8FE0B0@xxxxxxxxxxxxxxxx
> > > > > Hi Jan -
> > > > >
> > > > > Thanks for the response. How do you change the date for the status
> > line?
> > > > > Also I'm needing a date range versus one day. I think I'm going to
> > have
> > > > to
> > > > > learn macros.
> > > > >
> > > > > "Jan De Messemaeker" wrote:
> > > > >
> > > > > > Hi Heather,
> > > > > >
> > > > > > Through Format, Gridlines, you can define some vertical linessuch as
> > for
> > > > > > Project Start or Status Date; if you do not use the status date for
> > > > other
> > > > > > purposes, you can set it at any date you want to draw the vertical
> > line
> > > > you
> > > > > > want.
> > > > > >
> > > > > > --
> > > > > > Jan De Messemaeker
> > > > > > Microsoft Project Most Valuable Professional
> > > > > > http://users.online.be/prom-ade/
> > > > > > +32-495-300 620
> > > > > > "Heather" <Heather@xxxxxxxxxxxxxxxxxxxxxxxxx> schreef in bericht
> > > > > > news:692A90B3-3E46-4FA4-97BD-AA0D25134F23@xxxxxxxxxxxxxxxx
> > > > > > > I've worked with Project for three years now, and recall that you
> > can
> > > > add
> > > > > > > vertical bars in the gantt view to highlight the duration of an
> > event
> > > > > > > throughout the entire file (helps to highlight possible conflict
> > > > areas).
> > > > > > I
> > > > > > > cannot recall if it can be done without writing a macro. I
> > believe
> > > > when I
> > > > > > > worked with it before the vertical bars came through after running
> > a
> > > > > > macro.
> > > > > > > But if it can be done without running a macro, I would prefer to
> > do
> > > > that.
> > > > > >
> > > > > >
> > > > > >
> > > >
> > > >
> > > >
> >
> >
> >
.
- Follow-Ups:
- Re: vertical bars in gantt view (MS Project)
- From: Jan De Messemaeker
- Re: vertical bars in gantt view (MS Project)
- References:
- Re: vertical bars in gantt view (MS Project)
- From: Jan De Messemaeker
- Re: vertical bars in gantt view (MS Project)
- From: Jan De Messemaeker
- Re: vertical bars in gantt view (MS Project)
- From: Heather
- Re: vertical bars in gantt view (MS Project)
- From: Jan De Messemaeker
- Re: vertical bars in gantt view (MS Project)
- From: Heather
- Re: vertical bars in gantt view (MS Project)
- Prev by Date: Re: Keep Task Days Together
- Next by Date: Re: Weird bug in MS Project 2003 Resource Leveling
- Previous by thread: Re: vertical bars in gantt view (MS Project)
- Next by thread: Re: vertical bars in gantt view (MS Project)
- Index(es):
Relevant Pages
|
Loading