Re: Finish Date does not change
- From: John <mjensen@xxxxxxxxxxxx>
- Date: Fri, 23 Dec 2005 09:07:28 -0700
In article <3326ubb.20h97s@xxxxxxxxxxxxx>,
3326ubb <3326ubb.20h97s@xxxxxxxxxxxxx> wrote:
> In one particular schedule made by me, Calculation options for master
> all radio buttens are clicked as I want the unscheduled work to be
> scheduled forward from status date. Also calculation mode is clicked as
> Automatic.
> Still when I change % completion from 0% to any other %, the
> start/finish dates are not changing, which was happening yesterday in
> the same file.
> What should I do ?
> Please note that for the other files on the same client, the dates are
> changing with the same options.
> please help
3326ubb,
It isn't real clear what you mean by, "... calculation option for master
all ratio buttens are clicked...", but you might want to take a look at
the Actual Start field. It is possible to have an entry in that field
and still have the % Complete field showing "0%". And with an entry in
the Actual Start field, the task will be "locked" from moving.
John
Project MVP
.
- Prev by Date: Re: Keep Task Days Together
- Next by Date: Re: Updating the resource pool from a macro
- Previous by thread: Re: Keep Task Days Together
- Next by thread: Re: Finish Date does not change
- Index(es):