Re: Tasks span month ends, need costs for one month

Tech-Archive recommends: Repair Windows Errors & Optimize Windows Performance



In article <690FA0D1-2ECB-48A7-A424-70C826843CA2@xxxxxxxxxxxxx>,
"Chris V" <ChrisV@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote:

> > Chris,
> > I think we have a communication problem. First, what exactly do you
> > want? I though you wanted cost by month - either of the Usage views will
> > give you that depending on whether you want it by resource or by task.
> > Second, what do you mean by "closed" task? Third, what are you trying to
> > filter?
> >
> > With a little better understanding of your end goal, we can probably
> > come up with a solution.
> >
> > John
> > Project MVP
> >
>
> John,
>
> Iâ??ll start by clarifying â??closedâ??. Closed is the marked field, I have
> changed this column name to Closed. When Closed is Yes, this indicates
> contracts that have been accepted by the client and us therefore are a 100%
> go. This is what I am trying to filter on, only tasks that have a Yes value
> in the marked field.
>
> Is this the best way to handle this concept? Is this a proper use of the
> marked field?
>
> The final result I want is the task costs for work spilt by month where the
> marked field (Closed) is Yes. I want the rollup to show the total for only
> the filtered tasks, this is not happening
>
> Currently the rollup total cost shows all tasks, including those where
> Closed is No, even though these tasks do not appear in the filtered view.
> After manually adding the costs of the tasks in the filtered Usage view I get
> the correct value but the rollup total at the top (for the month) shows a
> larger value because it is including the Closed = No tasks.
>
> There are two tasks that have been identified as the difference between the
> rollup cost for the month and a manual total of the tasks that are listed in
> the filtered view. These tasks are marked No, do not appear in the task list
> of the filtered Usage view but are included in the rollup cost for the month.
>
> Put simply, the rollup totals are not respecting the filter even though the
> â??sub-tasksâ?? are.
>
> I hope Iâ??ve been clear and used the correct terms. Thank you for your time
> and help with this matter!
>
> Chris.

Chris,
Wow! what a difference a few words of clarification make with regard to
understanding the problem.

Using the Marked field is fine but you could also use one of several
other spare fields (e.g. FlagX). One unique thing about the Marked field
is that it can be used for special formatting (e.g. font color) for a
number of tasks - spare flag field can't do that.

Ok, here's a process you can use to display what you want.
1. In the Task Usage view, go to Project/Group by/Customize Group By.
2. Set the group criteria for the Marked field. (Note: you can save this
group for future use by hitting the "Save" button before hitting "OK" in
the Custom Group By window.)
3. Set up a filter for the Marked field.
4. When the filter and group are applied together, you should have the
monthly rollup you need.

Hope this helps.
John
Project MVP
3.
.



Relevant Pages

  • Re: Login attacks
    ... In the time when my only tool to filter this was an ip ... I do recall that it came to a screeching halt when korea, ... seem to want to count the cost to us since the cost to us is a profit ... Copyright 2004 by Maurice Eugene Heskett, ...
    (Fedora)
  • Re: Filtering a main form based on a sub-form
    ... search by project or search by cost center. ... combobox that lets me select a main-form record (either a specific employee, ... I want to be able to filter on cost ... center "10" in the sub-form and instead have the filter apply to the main ...
    (microsoft.public.access.forms)
  • Re: Truck suggestions please
    ... Fuel filter schedule on a Ford PS, is 15000 miles. ... I've over 200,000 miles in two Powerstrokes, and neither has cost me ... What did you say it costs you to change that oil every 3K miles? ...
    (rec.outdoors.rv-travel)
  • Re: OT: Need filter for dialysis (was Re: Help Request)
    ... passes the cost back to the persons local telco via interconnect charges, ... This is extremely common. ... looking into it in depth) that a filter for a dialisis machine is NOT ... > cost even if they can't donate cash. ...
    (RedHat)
  • Re: Network Diagram
    ... Thanks, Julie. ... In the Gantt chart insert the Marked field into the table ... by choosing Insert> Column and selecting the Marked field in the Insert ... Create a filter to show only marked tasks by going to Project> ...
    (microsoft.public.project)