Re: Change the default Project Calendar
- From: "scott_hane***" <scotthane***@xxxxxxxxxxxxxxxxxxxxxxxxx>
- Date: Mon, 19 Dec 2005 06:40:04 -0800
I agree with you in almost all cases (there are a very few specific cases I
am not sure about). I was actually more interested in knowing how to change
it to the night shift, and just put down 24hr because I didn't think it
effected my question.
One example of a 24 hr callendar I can think of is: You have three guys
each working a different shift in 24/7 environment. They are the only people
involved in the project and they have the same skill set. In this case I
think a 24hr calender would be more acurate. You would of course assign a
different callendar to each resource to reflect thier individual shifts.
Another situaltion would be if you have 24/7 production with 20 on 1st, 10
on 2nd, and 10 on 3rd. Each shift has aproximatly the same skill set. A
normal task could then be worked on for an average of 16 hours a day. 8 on
1st, and another 8 on either 2nd or 3rd. In this case it may be better to
use an 16hr base callendar.
Thanks for making sure I realize what I am doing.
Scott Hane***
"Steve House [Project MVP]" wrote:
> Careful doing that. The 24 hour calendar means that when a task begins it
> doesn't get interrupted for any reason until it ends. Since the work should
> be broken down to the level of one task = work done by one resource or team
> of resources working together as a unit, if you have Task X lasting one week
> and you assign Joe to do it, that means he'll work 24/7 without a meal
> break, without a nap, without seeing his kids for an entire week. Machines
> may work like that but people don't. Ah! but you say "We have round the
> clock shifts!" Each shift should get its own calendar - day shift, swing
> shift, and grave shift. IMHO, the "Project Calendar" should not reflect the
> hours of business of the firm or the hours during which work can be done by
> all shifts put together, it should reflect the normal work schedule of the
> most typical or generic worker on your project. That way when you put in a
> task of "XXX" duration, it will show in the schedule with timing at least
> somewhat close to what it will end up being in real life when the work is
> actually done by Joe Resource who is the sole person working on it. If I
> have a task that will require 24 hours to do, starting Monday at 8am, when I
> put it in the schedule it will start Mon @ 8 and end Wed @ 5. If I assign
> Joe Dayshift alone to do it, it starts and ends the same. But if I assign
> Joe Dayshift, Bill Swingshift, and Fred Graveshift that same 24 hour long
> task, its ending date will move from Wed @ 5 to now end Tue @ 8 after having
> run continuously for 24 hours as one shift relieved the other on it. This,
> to me, is a more accurate prediction of reality and a more accurate model of
> what will happen as you assign and reassign resources than what you'd get
> trying to use the 24 hour calendar as the project calendar.
>
> --
> Steve House [MVP]
> MS Project Trainer & Consultant
> Visit http://www.mvps.org/project/faqs.htm for the FAQs
>
>
> "scott_hane***" <scotthane***@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
> news:7FE643C2-ECA9-448C-AC8D-0671F1E5C494@xxxxxxxxxxxxxxxx
> >I want to know how to change the default Project Calendar from standard to
> >24
> > hours. I know how to assign a specific calendar for a specific resource
> > or
> > task and how to change the default settings on the calendar but I don't
> > know
> > how to change the overal Project Calendar from Standard to one of the
> > other
> > two.
> >
> > Thanks,
> > Scott Hane***
>
>
.
- Follow-Ups:
- Re: Change the default Project Calendar
- From: Steve House [Project MVP]
- Re: Change the default Project Calendar
- References:
- Re: Change the default Project Calendar
- From: Steve House [Project MVP]
- Re: Change the default Project Calendar
- Prev by Date: Re: Project Filter 'Highlight' View
- Next by Date: Re: MS Project - Allocating Resources (Human)
- Previous by thread: Re: Change the default Project Calendar
- Next by thread: Re: Change the default Project Calendar
- Index(es):
Loading