Re: Removing Summary Tasks from Network Diagram

Tech-Archive recommends: Repair Windows Errors & Optimize Windows Performance



Hello Steve,
It's not possible to actually remove the summary tasks in the network, but
you can do the following:
Format / Layout / Layout mode : Manual
Then you drag the summaries in a page which will not be print.

Hope this helps,

Gérard Ducouret

"Steve Adams, PMP" <SteveAdamsPMP@xxxxxxxxxxxxxxxxxxxxxxxxx> a écrit dans le
message de news:2260D9AE-D1F4-42DE-B34F-381BB6192A51@xxxxxxxxxxxxxxxx
> I'd like to remove the clutter of summary tasks from the Network Diagrm. I
> only want to see tasks as we do not add predecessors or sucessors to
summary
> tasks.
>
> Any ideas. Thanks in advance! I already tried turning off Show Summary
Tasks
> in Tools, Options.


.