Re: Summary tasks %comp don't update when subtask %comp data is en

Tech Tip: Click here to run a free scan for Windows Errors and optimize PC performance



In article <43530B0B-B3B9-4457-948A-C28864D37EFD@xxxxxxxxxxxxx>,
"jj" <jj@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote:

> John,
>
> Thanks for the help. Yes auto calculate is ON, and no the subtasks are not
> milestones. I have used Project fro several years but am not an expert. Just
> have gotten by by getting out of it what I needed. However this is the first
> time have have seen this situation. Problem is I have a couple of newbies
> also using this project so they could have, in their zealous effrots, gotten
> into areas of the project I know nothing about. So if you have any other
> ideas please let me know.
>
> JJ
>
> "John" wrote:
>
> > In article <5D7D6026-E6FB-47A3-BFBF-C2B5A71B78A4@xxxxxxxxxxxxx>,
> > "jj" <jj@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote:
> >
> > > standard 2003 office. Why is this happening?
> >
> > jj,
> > Well, without further information all I can do is take a stab at two
> > possible causes. First, is calculation set for automatic
> > (Tools/Options/Calculation tab)? Second, is the subtask being "updated"
> > a milestone?
> >
> > John
> > Project MVP
> >

jj,
Guess what, I've used Project for several years and I'm not an expert
either, so don't feel left out.

Let's take a look at some other possibilities. Do you have any links on
the summary task itself? Are all tasks under the summary line accounted
for (i.e. are all subtask IDs contiguous)? Are there any externally
linked subtasks under the summary?

Or, if you want, you can e-mail me the file and I can take a look at it.
If it has sensitive information, you can download a simple macro by
fellow MVP, Jack Dahlgren, that will remove sensitive information.
Jack's website is at:
http://masamiki.com/project/macros.htm
Look for the macro called "scrub"

John
Project MVP
.



Relevant Pages

  • Re: Can MSP show multiple tasks/milestones on one line in the Gant
    ... "John" wrote: ... On the Task Information box for the summary task, check the "Hide Task Bar" ... On the Task Information box for the tasks and milestones, ... Project MVP ...
    (microsoft.public.project)
  • Re: create a view like task usage
    ... features, but they are afraid of it right now. ... Also the milestones have due dates that trigger off several static dates ... "John" wrote: ... >> to get what I want from a custom report. ...
    (microsoft.public.project)
  • Re: No task display unless I make it a subtask
    ... > milestone nor are the subtasks under a summary only a list of milestones ... Summaries and milestones are just there ... but it still doesn't give me a task mark when I enter a new item. ...
    (microsoft.public.project)
  • Re: Transposing Tasks in a Report (summarizing common tasks)
    ... subtasks (milestones for those projects). ... individual tasks out in a report, per project, instead of projects, per task. ...
    (microsoft.public.project)
  • Re: Milestones add time to projects?
    ... The best solution is to completely remove the fixed-date constraint from your milestone and link it into the chain of subtasks as the last task in the chain. ... The duration of a summary is from the start of the earliest task to the finish of the latest task, If I have a summary containing only two subtasks, both of them milestones of zero duration, and use a MSO or MFO contraint to fix the subtasks to dates 2 weeks apart, the summary will show a duration of 2 weeks. ... are somehow adding time to each sub-project. ...
    (microsoft.public.project)