Hi Bigbad,
In what sense is opening all projects into a master a pain?
It is an option when opening the pool, no effort is needed whatsoebver.
HTH
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"Big_Bad_Yellow_Eskimo" <BigBadYellowEskimo@xxxxxxxxxxxxxxxxxxxxxxxxx>
schreef in bericht
news:47A0DAD9-B9EC-47A1-A4D0-686B4CE87F58@xxxxxxxxxxxxxxxx
> It would be very nice to be able from the Resource Usage View to select a
> specific Resource and then produce a Gantt View for that resource only. Of
> course, applying filters such as date range would also have to work.
> Obviously, I'm talking about doing this for a Resource Pool. When the pool
is
> large and multiple Projects are attached to it (it's my case), opening all
> the projects into a single project is a pain and it is not necessarily all
> the resources that need to have its own Gantt view.
>
> ----------------
> This post is a suggestion for Microsoft, and Microsoft responds to the
> suggestions with the most votes. To vote for this suggestion, click the "I
> Agree" button in the message pane. If you do not see the button, follow
this
> link to open the suggestion in the Microsoft Web-based Newsreader and then
> click "I Agree" in the message pane.
>
>
http://www.microsoft.com/office/community/en-us/default.mspx?mid=47a0dad9-b9
ec-47a1-a4d0-686b4ce87f58&dg=microsoft.public.project
.
- Prev by Date: Re: Limiting Client View of Project
- Next by Date: Re: Milestones delay entering
- Previous by thread: Re: Limiting Client View of Project
- Next by thread: Re: Resource Usage View to Gantt View
- Index(es):
Relevant Pages
|