Re: Subverting scheduling detail - plan & track by quarter




Hi Dan,

Glad you've found what you want. You could also level with a month-by-month
granularity which could go part way to what you want.

Thanks for your kind words on my series in TechTrax :) I hope you have
rated them for me!


Mike Glen
Project MVP



Dan_W wrote:
> Thanks Mike - I figured out that the main thing I needed to do was
> turn the automatic leveling off and change the time scale to Quarters
> & Quarters). I can then set the start date for the beginning of a
> quarter then allocate days of work and view the tally by quarter with
> the Resource Usage table. I ignore the fact that the top row (the
> sum) of the Resource Usage table is red (it thinks I'm double or
> triple booked each day) and instead just compare the total # days
> quarter to the # of days that I know are available for each resource.
>
> Also - I wanted to mention how tremendously helpful your TechTrax
> articles have been to me as I've been teaching myself Project - the
> best guidance series I've found through various web searches. Thanks!
>
> "Mike Glen" wrote:
>
>>
>> Hi Dan,
>>
>> Welcome to the Microsoft Project newsgroup :-)
>>
>> Have you had a look at the Resource Graph view? This should give
>> you what you want. If you want to aggregate more than one resource,
>> see FAQ Item:
>> 38. Combined Resource Graph
>>
>> FAQs, companion products and other useful Project information can be
>> seen at this web address: http://project.mvps.org/faqs.htm
>>
>> Hope this helps - please let us know how you get on:-)
>>
>> Mike Glen
>> Project MVP
>>
>> Dan_W wrote:
>>> I have used Microsoft Project to create a detailed list of tasks,
>>> assigned resources to all tasks and entered work days per resource
>>> per task. The resources working on this project have variable and
>>> unpredictable schedules that make it impossible to schedule their
>>> work on specific calendar days. Instead, I want to schedule work in
>>> terms of requested task-work-days per quarter (ideally bi-monthly
>>> but this does not appear to be an available unit) then evaluate
>>> whether we have sufficient resources to accomplish the work (e.g.,
>>> Resource A has 60 days/quarter available but is being asked to
>>> contribute to 10 tasks totaling 80 days in Qtr 1). I'm only
>>> interested in person-work-days per quarter (that's "Work" days and
>>> NOT "Duration" days) and specific start & end dates within a
>>> quarter are meaningless. My needs are pretty simple but I cannot
>>> figure out an approach in Project to plan by quarter and determine
>>> if we are over or under resourced by quarter.



.



Relevant Pages

  • RE: Scheduling and tracking question
    ... not ahead of schedule assuming the work estimate of 5% was correct. ... that you can do this by creating a separate column such as [Time Card Hours] ... There's more to it than that, becuase this will have to be done in Resource ... YOu may find FAQ #7 and FAQ #37 helpful. ...
    (microsoft.public.project)
  • Re: Subverting scheduling detail - plan & track by quarter
    ... Thanks Mike - I figured out that the main thing I needed to do was turn the ... of work and view the tally by quarter with the Resource Usage table. ... If you want to aggregate more than one resource, see FAQ Item: ... >> unpredictable schedules that make it impossible to schedule their ...
    (microsoft.public.project)
  • Re: Removing resource with unfinished tasks
    ... The resource Jim L is assigned full time during some days and ... When you *replace* Jim L by Dan, Ms Project replace Jim L only on the ... >>> Reid McTaggart ...
    (microsoft.public.project)
  • Re: Create a database when a user logs in for the first time
    ... Chris Hanscom - Microsoft MVP ... Veign's Resource Center ... > "dan" wrote: ... >> user does not have a DATABASE it creates one then creates a table in the ...
    (microsoft.public.vb.database)
  • Re: IAS events
    ... IMO, it's the best resource on the net. ... Dan ...
    (microsoft.public.win2000.security)