Re: Task Dependency
- From: "omar" <omar@xxxxxxxxxxxxxxxxxxxxxxxxx>
- Date: Tue, 6 Sep 2005 17:19:26 -0700
Julie S: Under tools>tracking>Save Baselines ~ I do have it saved for the
entire project.
Steve House: When I am talking about two different projects - I mean two
entirely separate task lists, each in its own mpp file. To better explain you
what I am doing: We have lot of projects with running with separate task list
and we are linking the the task to a Global Master. And on the global master
the start date and finish date gets updated but not the Baselines.
thank you
"Steve House [Project MVP]" wrote:
> Just to help clarify your question, some people use the term "project" to
> mean a summary task although that's not really the correct terminology.
> When you say "project" are you talking about to entirely separate task
> lists, each in its own mpp file or are you talking about two major groups of
> tasks indented under their own "project name" headings but all in the same
> mpp file?
> --
> Steve House [MVP]
> MS Project Trainer & Consultant
> Visit http://www.mvps.org/project/faqs.htm for the FAQs
>
>
> "omar" <omar@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
> news:41FC7BD4-E9BE-4875-84AD-2917E406179D@xxxxxxxxxxxxxxxx
> > How do you save the baseline for the entire project? I have two different
> > projects. I am just saving the baseline for the predecessor which is
> > linked
> > to the successor.
> > thanks
> > omar
> >
> > "JulieS" wrote:
> >
> >> Hi Omar,
> >>
> >> If you save the baseline for the entire project which contains the
> >> successor, the task will be baselined as well. Once a baseline is saved,
> >> it
> >> doesn't get changed unless you re-baseline.
> >>
> >> Hope this helps.
> >>
> >> Julie
> >> "omar" <omar@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
> >> news:A66F2D4B-481E-4BAC-9D95-8394AD8FBC99@xxxxxxxxxxxxxxxx
> >> > Thank you for your reply. Is there no way to automatically save the
> >> > baseline
> >> > for the successor? The successor is kept for the executives to view and
> >> > whatever changes an engineer makes in the predecessor would get updated
> >> > in
> >> > the successor.
> >> >
> >> > thank you
> >> >
> >> > "JulieS" wrote:
> >> >
> >> >> Hi Omar,
> >> >>
> >> >> Pardon me for jumping in.
> >> >>
> >> >> It appears as though you haven't saved the baseline for the successor
> >> >> task.
> >> >> Select the successor task and save the baseline (Tools>Tracking>Save
> >> >> baseline click "Selected task). You should now see the baseline Start
> >> >> and
> >> >> Finish fields populate with dates.
> >> >>
> >> >> Hope this helps. Let us know how you get along.
> >> >>
> >> >> Julie
> >> >>
> >> >> "omar" <omar@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
> >> >> news:FD1B1FA6-4A4C-4204-BCB4-D3026BD08694@xxxxxxxxxxxxxxxx
> >> >> > Ok here is what I am trying to do:
> >> >> > I have two projects and I linked a task from one project to the
> >> >> > other.
> >> >> > In
> >> >> > the predecessor, I changed the duration of the project and in turn
> >> >> > it
> >> >> > updated
> >> >> > the finish date. I manually saved the baselines so that everything
> >> >> > gets
> >> >> > updated. On the Successor, only the start date and finish date gets
> >> >> > updated
> >> >> > but the baselines remains NA. Why is it like that?
> >> >> >
> >> >> > thank you
> >> >> >
> >> >> > "Rod Gill" wrote:
> >> >> >
> >> >> >> So what are you expecting to see and what isn't happening. Please
> >> >> >> explain
> >> >> >> more what your question is about and how to reproduce it..
> >> >> >>
> >> >> >> --
> >> >> >>
> >> >> >> Rod Gill
> >> >> >> Project MVP
> >> >> >> Visit www.msproject-systems.com for Project Companion Tools and
> >> >> >> more
> >> >> >>
> >> >> >>
> >> >> >> "omar" <omar@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
> >> >> >> news:DEACC6A6-D3D1-4D39-ABE0-5FCF699697CC@xxxxxxxxxxxxxxxx
> >> >> >> > When tasks between two projects, why doesnt all the custom fields
> >> >> >> > show?
> >> >> >> > (I
> >> >> >> > mean some custom field stays NA)
> >> >> >>
> >> >> >>
> >> >> >>
> >> >>
> >> >>
> >> >>
> >>
> >>
> >>
>
>
.
- Follow-Ups:
- Re: Task Dependency
- From: JulieS
- Re: Task Dependency
- References:
- Task Dependency
- From: omar
- Re: Task Dependency
- From: Rod Gill
- Re: Task Dependency
- From: omar
- Re: Task Dependency
- From: JulieS
- Re: Task Dependency
- From: omar
- Re: Task Dependency
- From: JulieS
- Re: Task Dependency
- From: omar
- Re: Task Dependency
- From: Steve House [Project MVP]
- Task Dependency
- Prev by Date: Standard Project Template
- Next by Date: Re: Limitations in MS Project 2003?
- Previous by thread: Re: Task Dependency
- Next by thread: Re: Task Dependency
- Index(es):
Relevant Pages
|