Re: Task Dependency

Tech-Archive recommends: Fix windows errors by optimizing your registry



Julie S: Under tools>tracking>Save Baselines ~ I do have it saved for the
entire project.

Steve House: When I am talking about two different projects - I mean two
entirely separate task lists, each in its own mpp file. To better explain you
what I am doing: We have lot of projects with running with separate task list
and we are linking the the task to a Global Master. And on the global master
the start date and finish date gets updated but not the Baselines.

thank you

"Steve House [Project MVP]" wrote:

> Just to help clarify your question, some people use the term "project" to
> mean a summary task although that's not really the correct terminology.
> When you say "project" are you talking about to entirely separate task
> lists, each in its own mpp file or are you talking about two major groups of
> tasks indented under their own "project name" headings but all in the same
> mpp file?
> --
> Steve House [MVP]
> MS Project Trainer & Consultant
> Visit http://www.mvps.org/project/faqs.htm for the FAQs
>
>
> "omar" <omar@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
> news:41FC7BD4-E9BE-4875-84AD-2917E406179D@xxxxxxxxxxxxxxxx
> > How do you save the baseline for the entire project? I have two different
> > projects. I am just saving the baseline for the predecessor which is
> > linked
> > to the successor.
> > thanks
> > omar
> >
> > "JulieS" wrote:
> >
> >> Hi Omar,
> >>
> >> If you save the baseline for the entire project which contains the
> >> successor, the task will be baselined as well. Once a baseline is saved,
> >> it
> >> doesn't get changed unless you re-baseline.
> >>
> >> Hope this helps.
> >>
> >> Julie
> >> "omar" <omar@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
> >> news:A66F2D4B-481E-4BAC-9D95-8394AD8FBC99@xxxxxxxxxxxxxxxx
> >> > Thank you for your reply. Is there no way to automatically save the
> >> > baseline
> >> > for the successor? The successor is kept for the executives to view and
> >> > whatever changes an engineer makes in the predecessor would get updated
> >> > in
> >> > the successor.
> >> >
> >> > thank you
> >> >
> >> > "JulieS" wrote:
> >> >
> >> >> Hi Omar,
> >> >>
> >> >> Pardon me for jumping in.
> >> >>
> >> >> It appears as though you haven't saved the baseline for the successor
> >> >> task.
> >> >> Select the successor task and save the baseline (Tools>Tracking>Save
> >> >> baseline click "Selected task). You should now see the baseline Start
> >> >> and
> >> >> Finish fields populate with dates.
> >> >>
> >> >> Hope this helps. Let us know how you get along.
> >> >>
> >> >> Julie
> >> >>
> >> >> "omar" <omar@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
> >> >> news:FD1B1FA6-4A4C-4204-BCB4-D3026BD08694@xxxxxxxxxxxxxxxx
> >> >> > Ok here is what I am trying to do:
> >> >> > I have two projects and I linked a task from one project to the
> >> >> > other.
> >> >> > In
> >> >> > the predecessor, I changed the duration of the project and in turn
> >> >> > it
> >> >> > updated
> >> >> > the finish date. I manually saved the baselines so that everything
> >> >> > gets
> >> >> > updated. On the Successor, only the start date and finish date gets
> >> >> > updated
> >> >> > but the baselines remains NA. Why is it like that?
> >> >> >
> >> >> > thank you
> >> >> >
> >> >> > "Rod Gill" wrote:
> >> >> >
> >> >> >> So what are you expecting to see and what isn't happening. Please
> >> >> >> explain
> >> >> >> more what your question is about and how to reproduce it..
> >> >> >>
> >> >> >> --
> >> >> >>
> >> >> >> Rod Gill
> >> >> >> Project MVP
> >> >> >> Visit www.msproject-systems.com for Project Companion Tools and
> >> >> >> more
> >> >> >>
> >> >> >>
> >> >> >> "omar" <omar@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
> >> >> >> news:DEACC6A6-D3D1-4D39-ABE0-5FCF699697CC@xxxxxxxxxxxxxxxx
> >> >> >> > When tasks between two projects, why doesnt all the custom fields
> >> >> >> > show?
> >> >> >> > (I
> >> >> >> > mean some custom field stays NA)
> >> >> >>
> >> >> >>
> >> >> >>
> >> >>
> >> >>
> >> >>
> >>
> >>
> >>
>
>
.



Relevant Pages

  • Re: Status Indicator
    ... Thanks Julie. ... the Status field in Project does not reference the baseline. ... This status indicator is calculated according the end of the ... task is behind schedule". ...
    (microsoft.public.project)
  • Re: How can I show that a task was finished ahead of time?
    ... Julie ... The baseline finish will not ... The finish date showing in the schedule will equal the ...
    (microsoft.public.project)
  • Re: multiple baselines gantt
    ... > You are right you are limited to four rows but the Multiple Baseline ... >> Hi Julie, ... >> Project MVP ... Use the existing bar style definitions as a guide ...
    (microsoft.public.project)
  • Re: Baseline
    ... Julie ..... ... Changing the baseline is still not completed. ... Data in the resource Start field into the resource Baseline Start field ... Data in the assignment Start field into the assignment Baseline Start ...
    (microsoft.public.project)
  • Re: How do I re-baseline a project schedule?
    ... It is not necessary to clear the original baseline. ... You should not be entering ...
    (microsoft.public.project)