Re: Schedule from End Date



Steve, Thank you for your excellent post. I switched between having MS
project schedule from the start date and the finish date and saw the latest
date I can start the project. I want to be able to change the deadline for
the last task and see the start date moving as I change the deadline but that
does not seem to change as I change the deadline.

"Steve House [Project MVP]" wrote:

> It sounds like what you want to do is see what the latest possible date you
> might start would be and still finish the project by a certain end date.
> Remember you can switch the "schedule from" entry in the Project Information
> menu back and forth between scheduling from start and scheduling from finish
> as many times as you want. I'd lay out my schedule from the start date and
> let the finish fall where it may - I find it's easier to think about what
> needs to be done and what order to do them if you're thinking start to
> finish. After I've created the project task outline itlself and linked the
> tasks into the order they need to be done, I'd switch to "schedule from
> finish", enter the required finish date, and see where it put the start
> date. Now switch back the "schedule from start" and you'll see that it will
> have reset the start date for you to the latest possible date you could
> start and still meet the required finish. That would be the theoretical
> latest possible start date but I'd never wait until that date to begin work.
> If you did, and something caused any task to get delayed - and you can count
> on the fact that something will always get delayed - it would mean that your
> project would finish late. So I'd pick a reasonable start date sooner than
> the latest possible start date reset the start to the date I'd picked.
> Meanwhile I'd put a deadline on the finish task of the required finish date
> so if something happens that will make me miss that deadline it'll get red
> flagged early enough for me to do something to fix it.
>
> There's some differences of opinion about this but I'd never, ever, use a
> "must finish on" or "must finish no later than" constraint to represent the
> date the project needs to be done. The reason is that the constraint DOES
> NOT mean "this is when it is supposed to happen." Rather, it means "this is
> when it WILL happen" and instructs Project to lock it onto that date and
> display it happening then regardless of anything else we do in organizing
> the schedule! Since the reason for using scheduling software in the first
> place is to figure out how to organize your project to meet your business
> objectives, I suggest it's usefullness is severely compromised if you
> disable its ability to tell you if you're succeeding or failing. It seems
> logical to me that if you've screwed up and organized the work in such a way
> as to have the project finish several weeks past your required finish date,
> the software should tell you that you blew it by placing the calculated
> finish where your plan will have it fall and not lie to you and tell you
> it's on time when it won't be. Using a constraint instead of a deadline in
> effect tells Project to lie to you by locking the displayed finish date to
> the date you said you wanted. So why is the constraint option even there?
> Because there might be things happening in the project that really do happen
> on a certain timeframe that is fixed and not influenced by anything in the
> project schedule. Christmas Day really is a fixed date that happens on 25
> Dec and nothing we do in arranging our project's work is going to change it.
> Constraints lets you model that reality. But you simply can't say that the
> project actual finish is not going to be influenced by the way the project's
> work is organized and I suggest the plan should predict what you're going to
> get and not just parrot back what you want to get.
> --
> Steve House [MVP]
> MS Project Trainer & Consultant
> Visit http://www.mvps.org/project/faqs.htm for the FAQs
>
>
> "Hadi" <Hadi@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
> news:46174EB0-E133-4405-AA3E-DBDCD5C32485@xxxxxxxxxxxxxxxx
> >I want to build a schedule. I want to build it like this:
> >
> > - Have a task at the end of the project that has a must start constraint.
> > - I want to be able to move the this last task around and see what would
> > be
> > the latest date I can start the project to meet the start date i set. Is
> > there a way of doing that without setting up project to schedule from the
> > finish date. I thought I can do that by showing the late start date on
> > all
> > the activities and have it change as I move the last task around. help
> > plz I
> > have a deadline next tuesday and I would like to have an idea of how to do
> > this.
>
>
.



Relevant Pages

  • Re: Why it is better to not use Deadline dates
    ... schedule from finish date. ... > 4) The three tasks have the defaulted constraint "As soon as possible". ... > 6) Associate to task c a deadline date equal to 05/12/05 and then change ... > milestone d with 0 days of duration, you associate it a "Must start on" ...
    (microsoft.public.project)
  • Re: Event Scheduling deadline date
    ... Steve House [Project MVP] wrote: ... successor task finish is pushed past its deadline, ... accurately details what has been done to date and a forecast schedule ... ALAP constraint pushes the task to the end of any slack it may ...
    (microsoft.public.project)
  • Re: Schedule from End Date
    ... It's fine to schedule backwards to find the ... When you do, your finish milestone ... If delays move the finish milestone too close to the deadline for ... > this but I'm absolutely NOT a fan of using a "must finish on" constraint on ...
    (microsoft.public.project)
  • Re: Deadlines and Constraints
    ... > "Jan De Messemaeker" wrote: ... >> A deadline DOES NOT as such change the schedule of a task. ... >> Task A has a Finish No Later Than constraint of Wednesday. ...
    (microsoft.public.project)
  • Re: applying resource availability constraints to a finish date sc
    ... If you actually keep Project up to date during the project, it will start warning you about how the end date has slipped past the deadline. ... There a number of different ways to model the project due to availability. ... Project will compute the schedule based on that availability. ... My suggestion is to not think of resource availability as a "constraint". ...
    (microsoft.public.project)