Re: Task Dependency

Tech-Archive recommends: Speed Up your PC by fixing your registry



Hi Omar,

If you save the baseline for the entire project which contains the
successor, the task will be baselined as well. Once a baseline is saved, it
doesn't get changed unless you re-baseline.

Hope this helps.

Julie
"omar" <omar@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:A66F2D4B-481E-4BAC-9D95-8394AD8FBC99@xxxxxxxxxxxxxxxx
> Thank you for your reply. Is there no way to automatically save the
> baseline
> for the successor? The successor is kept for the executives to view and
> whatever changes an engineer makes in the predecessor would get updated in
> the successor.
>
> thank you
>
> "JulieS" wrote:
>
>> Hi Omar,
>>
>> Pardon me for jumping in.
>>
>> It appears as though you haven't saved the baseline for the successor
>> task.
>> Select the successor task and save the baseline (Tools>Tracking>Save
>> baseline click "Selected task). You should now see the baseline Start
>> and
>> Finish fields populate with dates.
>>
>> Hope this helps. Let us know how you get along.
>>
>> Julie
>>
>> "omar" <omar@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
>> news:FD1B1FA6-4A4C-4204-BCB4-D3026BD08694@xxxxxxxxxxxxxxxx
>> > Ok here is what I am trying to do:
>> > I have two projects and I linked a task from one project to the other.
>> > In
>> > the predecessor, I changed the duration of the project and in turn it
>> > updated
>> > the finish date. I manually saved the baselines so that everything gets
>> > updated. On the Successor, only the start date and finish date gets
>> > updated
>> > but the baselines remains NA. Why is it like that?
>> >
>> > thank you
>> >
>> > "Rod Gill" wrote:
>> >
>> >> So what are you expecting to see and what isn't happening. Please
>> >> explain
>> >> more what your question is about and how to reproduce it..
>> >>
>> >> --
>> >>
>> >> Rod Gill
>> >> Project MVP
>> >> Visit www.msproject-systems.com for Project Companion Tools and more
>> >>
>> >>
>> >> "omar" <omar@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
>> >> news:DEACC6A6-D3D1-4D39-ABE0-5FCF699697CC@xxxxxxxxxxxxxxxx
>> >> > When tasks between two projects, why doesnt all the custom fields
>> >> > show?
>> >> > (I
>> >> > mean some custom field stays NA)
>> >>
>> >>
>> >>
>>
>>
>>


.



Relevant Pages

  • Re: I entered predecessors which changed my start and finish dates
    ... Creating a predecessor of a task makes the task a successor to the ... Microsoft Project Most Valuable Professional ... And baselines chenge when you go to Tools, Tracking, Set baseline. ...
    (microsoft.public.project)
  • Re: Task Dependency
    ... I am just saving the baseline for the predecessor which is linked ... If you save the baseline for the entire project which contains the ... successor, the task will be baselined as well. ... Julie ...
    (microsoft.public.project)
  • Re: Task Dependency
    ... The successor is kept for the executives to view and ... "JulieS" wrote: ... > It appears as though you haven't saved the baseline for the successor task. ...
    (microsoft.public.project)
  • Re: I entered predecessors which changed my start and finish dates
    ... "Jan De Messemaeker" wrote: ... Creating a predecessor of a task makes the task a successor to the ... And baselines chenge when you go to Tools, Tracking, Set baseline. ...
    (microsoft.public.project)
  • Re: Task Dependency
    ... I am just saving the baseline for the predecessor which is linked ... > successor, the task will be baselined as well. ... >>> Julie ...
    (microsoft.public.project)