RE: Actual work from unopened projects not reflected in resource usage

Tech Tip: Click here to run a free scan for Windows Errors and optimize PC performance



You can use PWA to get your rollups of Actuals and other such data. The
behavior is not a bug because the tool was never designed to do what you want.

Showing all work across all projects is useful for planning assignments.
Analyzing Actuals is a retrospective analytical activity that is handled in
PWA.

I do agree that the advice to open all projects is not practical. It should
say to use PWA.
--
Reid McTaggart
EPM Architect
Microsoft


"MikeR" wrote:

> Hi All,
>
> I have a perplexing problem. It appears that when I open one or a few
> files (out of many) from Project Server, actual work from unopened projects
> is not reflected in the work rollup. See article 888638 on Microsoft's site
>
> http://support.microsoft.com/?scid=kb;en-us;888638&spid=2525&sid=global
>
> The suggested workaround is to open all files relating to the resource in
> question. While this works, this is impractical in my environment because:
>
> 1 - there are hundreds of files
> 2 - some files, such as those representing administrative time, were not
> meant to be managed by any other than a few admins (this is a current
> business practice of ours)
> 3 - I may not have access to every relevant file
>
> Is there another way around this? Anyone know of plans to fix it?
>
> As an aside, this behavior certainly looks like a bug to me - after all, it
> appears that I can see the planned work from unopened files just fine. The
> article cited above spins this as a "behavior" rather than a "problem" or
> "bug", though I haven't found any reference in the regular documentation that
> would lead to this conclusion. I would hope that someone is looking at a
> more satisfactory resolution than opening all files. Anyone out there have
> additional details on what might be in store?
>
> Thanks,
> Mike
.



Relevant Pages

  • RE: Actual work from unopened projects not reflected in resource u
    ... file, go to Resource Usage, select the resource I want to level, and have at ... But, actuals in other projects appear to be ignored, as per our ... Do you have a suggestion that would allow resource levelling to be used ... > You can use PWA to get your rollups of Actuals and other such data. ...
    (microsoft.public.project)
  • Re: Timetracking
    ... I agree with Dale another option is to use Adjust actuals screen in PWA ... Logon to PWA as you or project manager> Click on Resouce> Click on Adjust ... > name and password for each of these team members and enter their actuals. ...
    (microsoft.public.project.pro_and_server)
  • Re: Tracking Project Actuals for Enterprise
    ... you can certainly enter actuals in the actual ... your resources enter actuals in PWA. ... Select the "Overwrite actual work entered by resources" option ... "We wrote the book on Project Server" ...
    (microsoft.public.project.pro_and_server)
  • Re: Actuals gone
    ... Use Collaborate> Republish and republish all tasks selecting the Overwrite ... without protected actuals. ... > project plan.....but in our case they just don't appear on the timesheet. ... > inserted into the Work Hours fields for each day in PWA. ...
    (microsoft.public.project.pro_and_server)