RE: How do i calculate the difference between start and end dates?
- From: Joe <Joe@xxxxxxxxxxxxxxxxxxxxxxxxx>
- Date: Wed, 10 Aug 2005 11:06:06 -0700
I am not sure I fully understand why duration as calculated by MS project is
not what you are looking for. But based on your example, have you thought of
taking the difference of the Actual Start Date and Actual Finish Date fields?
You could probably set up a custom field to calculate this automatically.
But I think this calculation may end up giving you the same result as the
duration field would. It’s worth a try and compare the two.
"Dennis Meyer" wrote:
> I need to know how long it takes to deliver a task... not how many working
> hours are involved (duration as calcualted by MS Project), but what is the
> absolute difference between the start date/time and end date/time? I can
> manually count the number of days and hours between the start date and end
> date, but...
>
> For example, I start a task on Tues 7/5/05 8:00AM and finish it on Sun
> 7/17/05 7:39 PM. The time it took to deliver the task was 12 days and almost
> 12 hours. Project calculates duration as 15.71 days, because some resources
> work different shifts (8hrs, 12hrs, 10hrs). The duration as calculated is
> useful, but not exactly what I need.
>
> Anyone out there able to help?
>
> Thanks.
>
.
- References:
- How do i calculate the difference between start and end dates?
- From: Dennis Meyer
- How do i calculate the difference between start and end dates?
- Prev by Date: Re: Import MS Project tasks to Outlook task list
- Next by Date: Re: How do i calculate the difference between start and end dates?
- Previous by thread: How do i calculate the difference between start and end dates?
- Next by thread: Re: How do i calculate the difference between start and end dates?
- Index(es):
Relevant Pages
|