Half day task scheduling problem
- From: "TJ Beebe" <TJ Beebe@xxxxxxxxxxxxxxxxxxxxxxxxx>
- Date: Wed, 10 Aug 2005 11:17:02 -0700
First of all, I am a newbie to this software...
I have a project in which tasks are in increments of half days (4 hours).
When I start linking tasks with half day durations, Project will break the
work up into 5 hours for one task and 3 hours for the other, instead of
evenly distributing 4 hours and 4 hours. I have not changed the units from
100%. This presents a problem becasue it will cause the work associated with
2 half day tasks that were supposed to be completed in one day to be
completed over a 2 day duration (5 hours, 3 hours, and 1 hour the next day).
Please help me understand why this might be happening.
Thank you in advance for your help!
TJ Beebe
.
- Follow-Ups:
- Re: Half day task scheduling problem
- From: JulieS
- Re: Half day task scheduling problem
- Prev by Date: Re: How do i calculate the difference between start and end dates?
- Next by Date: Re: How do i calculate the difference between start and end dates?
- Previous by thread: Conditonally formatting tasks
- Next by thread: Re: Half day task scheduling problem
- Index(es):
Relevant Pages
|