Half day task scheduling problem

Tech-Archive recommends: Repair Windows Errors & Optimize Windows Performance



First of all, I am a newbie to this software...

I have a project in which tasks are in increments of half days (4 hours).
When I start linking tasks with half day durations, Project will break the
work up into 5 hours for one task and 3 hours for the other, instead of
evenly distributing 4 hours and 4 hours. I have not changed the units from
100%. This presents a problem becasue it will cause the work associated with
2 half day tasks that were supposed to be completed in one day to be
completed over a 2 day duration (5 hours, 3 hours, and 1 hour the next day).
Please help me understand why this might be happening.

Thank you in advance for your help!

TJ Beebe
.



Relevant Pages