Re: Remove a task from the critical path



Brian, thats right. The task is a "Project Management" task. I have added the
task in in so I can include my time in the estimated and actual cost figures.
My time is not on the critical path but it does span the entire project.
Thats why its a hammock task, linked to the end date.

Thanks

"Brian K - Project MVP" wrote:

> Kevin wrote:
>
> >Mike, I like your thinking :-) Problem is MSProject wont colour the real
> >critical path tasks red.
> >
> >Thanks
> >
> >"Mike Glen" wrote:
> >
> >>
> >>Hi Kevin,
> >>
> >>Welcome to this Microsoft Project newsgroup :-)
> >>
> >>A work-around is to format the bar as blue.
> >>
> >>FAQs, companion products and other useful Project information can be seen
> >>at
> >>this web address: http://www.mvps.org/project/
> >>
> >>Hope this helps - please let us know how you get on :-)
> >>
> >>Mike Glen
> >>Project MVP
> >>
> >> Kevin wrote:
> >>>How can you remove a task from the critical path? I have a hammock
> >>>task that moves with the end date, but its not critical. It moves
> >>>with the end date because its a support task that needs to keep going
> >>>as long as the project is going. However, because it extends to the
> >>>end of the project, MSProject is marking it as a critical task.
> >>>
> >>>Any ideas?
> >>
> >>
> >>
> >>
>
> Are you saying that you feel that the tasks Project has marked 'Critical'
> are not really critical?
>
> --
> Brian K - Project MVP
> http://www.projectified.com
> --
> Senior Trainer - Electronic Arts
> --
> QuantumPM Associate
> http://www.quantumpm.com
>
.



Relevant Pages

  • Re: # porgrams running when doing nothing
    ... Brian wrote: ... Thats seems like a lot. ... Where can I go to get help and knowing what ... Start | Run line, and on the Startup tab, uncheck the programs you don't ...
    (microsoft.public.windowsxp.perform_maintain)
  • Re: Unicycle Teacher Arrested On Sex Charges
    ... can testify in court on whether or not someone was sexually abusing ... the outcome of which can be years of jail and public ostricising ... thats not strange at all. ... Brian O.'s Profile: http://www.unicyclist.com/profile/10744 ...
    (rec.sport.unicycling)
  • Re: Good, Gawd! Not again!!!
    ... year and thats not saying much with loses to Vanderbilt and Kentucky. ... For Brian K's Las Vegas & Pictures Go To....... ...
    (alt.vacation.las-vegas)
  • Re: KH handle with Viscount
    ... JFoss should be able to tell you more about it. ... Oh yeah, just like that, I wasn't even aware that its been done before. ... I didn't think about bolting the handle through it too, thats great to ... Brian O.'s Profile: http://www.unicyclist.com/profile/10744 ...
    (rec.sport.unicycling)
  • Re: Remove a task from the critical path
    ... The hammock task is only there to show the project management effort, ... dtermine the critical path or influence it in any way. ... If thats not possible, can you suggest a better way of factorign Project ...
    (microsoft.public.project)

Quantcast