Re: How to force project not to split a task over multiple days
- From: "latearrival" <latearrival@xxxxxxxxxxxxxxxxxxxxxxxxx>
- Date: Thu, 7 Jul 2005 18:36:02 -0700
Thanks Mike. I'll have a play with this and let you know the results.
You're simpler suggestion of taking the workshop off the plan will not work
- I cannot make that day a non-working day because I do not have a fixed day
for the workshop. I want MS Project to tell me when to run the workshop based
on all the other constraints and assignments. My problem is exacerabated by
the fact that the project consists of lots of workshop-like tasks - i.e tasks
that (i) require equal contribution from all assigned resources and (ii) must
be of a specified, fixed duration.
I really appreciate everyone taking the time to reply.
Thanks
Dave.
"Mike Glen" wrote:
>
> Hi Dave,
>
> Welcome to this Microsoft Project newsgroup :)
>
> You could try making the workshop priority 1000 (do not level) and select
> Priority,Standard and allow splitting, in the Levelling dialog. Personally,
> I think it would be simpler to take the workshop off the project and set the
> project calendar to non working time for that day.
>
> FAQs, companion products and other useful Project information can be seen at
> this web address: http://www.mvps.org/project/
>
> Hope this helps - please let us know how you get on :)
>
> Mike Glen
> MS Project MVP
>
> latearrival wrote:
> > Some of the tasks in my plan are workshops, e.g with a duration of 1
> > day and multiple resources assigned. When levelling, Project keeps
> > splitting the task over multiple days due to the other tasks assigned
> > to these resources. e.g project schedules Fred on the workshop task
> > on Monday and Mary to the workshop task on Friday - I need them both
> > to attend the workshop on the same day! I want Project to calculate
> > the day when all the resources are free, not extend the duration of
> > the task. Anyone know how to do this in Project 2000?
> > Cheers
> > Dave.
>
>
>
>
.
- Follow-Ups:
- Re: How to force project not to split a task over multiple days
- From: Mike Glen
- Re: How to force project not to split a task over multiple days
- References:
- How to force project not to split a task over multiple days
- From: latearrival
- Re: How to force project not to split a task over multiple days
- From: Mike Glen
- How to force project not to split a task over multiple days
- Prev by Date: Re: Enterprise fields VS Views
- Next by Date: Re: Comparing resource names in VBA
- Previous by thread: Re: How to force project not to split a task over multiple days
- Next by thread: Re: How to force project not to split a task over multiple days
- Index(es):
Relevant Pages
|