Re: When the following exception comes
- From: "Jan De Messemaeker" <jandemes at prom hyphen ade dot be>
- Date: Fri, 1 Jul 2005 17:38:04 +0200
Hi,
If there is only one task, that one must have external links.
Delete them.
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
"Devender" <Devender@xxxxxxxxxxxxxxxxxxxxxxxxx> schreef in bericht
news:9B0B48E2-89FC-417C-8ABF-3D8B5ADC7D86@xxxxxxxxxxxxxxxx
> I got the following exception for the particular project TimeDataTest1
which
> has only one task Task1:
>
> No calculation can be performed now.
>
> There is a circular relationship in task 1 Task1 of TimeDataTest1. The
> successor of this task refers back to this task or its predecessors,
causing
> a circular reference.
>
> To move the link that is causing the circular reference, select the two
> tasks that are causing the circular link, then click Unlink Tasks on the
> standard toolbar.
> Does any one know what might cause this
> Devender
>
>
>
.
- References:
- When the following exception comes
- From: Devender
- When the following exception comes
- Prev by Date: Re: Longhorn?
- Next by Date: Re: Copying resources
- Previous by thread: When the following exception comes
- Next by thread: Formulas
- Index(es):
Relevant Pages
|