Re: Commenting work hours
Tech-Archive recommends: Fix windows errors by optimizing your registry
You could always teach your resources to date their entries in the
Notes field for the task. At a prior company, we used the Notes for the
Project Summary task to indicate any major changes to the project
schedule as a whole, and when updates were made. We simply entered the
date, our initials, and the comment. The next time you need to comment,
just use a new line (we went in reverse chronological order so the most
recent comment was always at the top).
Sarah
.
Relevant Pages
- Re: Saving Project with a note in the summary task.
... Brekada wrote: ... always double-click the summary task and go in the Notes tab. ... If the Project Summary Task ... Notes field for some unknown reason acts differently than the Notes ... (microsoft.public.project) - Re: Saving Project with a note in the summary task.
... Brekada wrote: ... always double-click the summary task and go in the Notes tab. ... If the Project Summary Task ... Notes field for some unknown reason acts differently than the Notes ... (microsoft.public.project) - Re: Saving Project with a note in the summary task.
... If the Project Summary Task ... Notes field for some unknown reason acts differently than the Notes ... if I double click the summary level task on the ... without the annoying message. ... (microsoft.public.project) - Re: Printing Notes
... first entry. ... When you say you have multiple entries in the Notes field I assume you ... Simply adding the Notes field as a column in a view will truncate at the ... (microsoft.public.project) - Re: Microsoft Project 2003 audit trail
... Another method is to show the Project Summary task, and train all ... users to use the Notes field for this task as a log. ... Sarah ... (microsoft.public.project) |
|