John, Thank you VERY much for your help! It looks like it's time to go buy
another book!

"John" wrote:

> In article <129C416E-EA30-4FCB-A1CA-F981EE1CF3A4@xxxxxxxxxxxxx>,
> "SignalwL" <SignalwL@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote:
>
> > I typically manually update tasks as a value in %complete or Work Complete as
> > I do not have the time to enter actuals for individual tasks. How can I have
> > Project reflect those values beside the roll-up task? Is there a way to
> > compare where I am vice where I should be at a certain time?
>
> SignalwL,
> I assume when you say, "...reflect those values beside the roll-up
> task", you mean you want to see the updated %Complete and %Work Complete
> automatically show up in the Summary Line data. All you have to do is to
> make sure calculation is set to automatic (Tools/Options/Calculation
> tab).
>
> As far as comparing current schedule performance to expect schedule
> performance, that is the main purpose of the earned value (EV) metrics
> (BCWP, BCWS, ACWP, SPI and CPI). However before you can make use of
> those metrics, which are automatically calculated by Project, you need
> to ensure a baseline has been set. For more information on EV metrics,
> check the Project help file.
>
> Hope this helps.
> John
> Project MVP
>
.



Relevant Pages

  • Re: Progress Line Date Question PLEASE HELP
    ... I would have thought that such a basic thing should be a standard ... The metrics of most interest are standard earned value metrics, BCWS, BCWP, ACWP, SV, CV, SPI and CPI. ... However, to answer your question, there are two forms of the DateAdd Method - one works with calendar time and the other works with Project calendar time. ... As John says, anything you want to do should be achievable through Earned Value figures. ...
    (microsoft.public.project)
  • Re: Can we twist a digital picture to be square with the camera?
    ... Gee, John, why should I "test it" for your metrics when it works ... I am not an optical bench-racer-bullshitter who doesn't work. ...
    (rec.photo.digital)
  • Re: % Complete vs. Work Complete in Project?
    ... > Project reflect those values beside the roll-up task? ... > compare where I am vice where I should be at a certain time? ... As far as comparing current schedule performance to expect schedule ... that is the main purpose of the earned value metrics ...
    (microsoft.public.project)
  • Re: Chopin Etude op. 10 #2 - Comparison Listening
    ... Perceptive, intelligent mini-essay from John. ... least musically relevant works to compare pianists in. ... with Chopin even the minor trifle is interesting (the odd modulation ...
    (rec.music.classical.recordings)
  • Re: How to suppress displaying an object
    ... John ... "Iain" wrote: ... > Compare with one of the fields from the task table ... >> Rgs, ...
    (microsoft.public.vb.crystal)