Lag time has unexpected length
- From: "AJennings" <ajennings@xxxxxxxxx>
- Date: 10 Jun 2005 08:52:49 -0700
Using Project 2003, I need to have a task called Certificate of
Acceptance to come 30 days after Commence System Acceptance Testing.
When I set a 30d value in the Predecessors tab of the Commence System
Acceptance Testing task, the Gantt chart shows the task finishing many
weeks later.
Why is this happening?
.